AI data center · Barker, New York

Core42 Lake Mariner

Core42's AI campus in Niagara County. It draws about 58 MW today.

Power now58 MWAs of Jul 23, 2026
Planned peak58 MWMarch 2026
Compute72kH100-equivalent chips now
Capital cost$2.2BSo far, 2025 dollars

Latest look · Jul 23, 2026

What the satellite shows

Both buildings still operational according to satellite imagery.

Build-out

Power, month by month

0 MW20 MW40 MW60 MW80 MW20252026
Power drawn by Core42 Lake Mariner, from Epoch AI's dated observations.
0 MW20 MW40 MW60 MW80 MW20252026
Power drawn by Core42 Lake Mariner, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Core42
Used by
G42 (likely)
Investors
Google
Chips
B200
Water use
0.00 million gallons a day (Epoch AI estimate)
Address
7725 Lake Rd, Barker, NY 14012
County
Niagara County

Where

On the map of New York

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Lockport Energy Associates● Natural gas221 MW14.8 mi
Slayton Settlement Road Solar CSG● Solar7 MW10.3 mi
Source Power NY III - Medina II (CSG)● Solar5 MW11.7 mi
Ruhlmann A (CSG)● Solar5 MW14.5 mi
Niagara (NY)● Solar4 MW11.8 mi
Hydraulic Race● Hydro3 MW13.1 mi
NY Ridgeway I CSG● Solar3 MW12.6 mi
Glenwood Hydro● Hydro2 MW13.3 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jul 23, 2026Both buildings still operational according to satellite imagery.58 MW
Mar 31, 2026Building 2 is operational. On February 26, Terawulf stated that CB2A is operational, presumably making up half the final capacity. CB2B was expected in March 2026. However, it's notable that a drone video commissioned from RAAD showed no cooling fan movement on May 8th, suggesting it was not in use. This building is leased to Core42, a subsidiary of UAE-based G42. It likely uses NVIDIA DGX B200 servers.58 MW
Mar 2, 2026Buildings 1 and 2 both appear to have complete building and cooling equipment, based on satellite imagery. Not considering Building 2 operational yet, due to Terawulf's statement that CB2B is expected in March 2026, and is likely still in commissioning phase.19 MW
Oct 1, 2025Building 1 is operational. Based on Terawulf saying "As of September 30, 2025, the site has energized 245 MW of Bitcoin-mining capacity and 22.5 MW of HPC capacity." The small "Wulf Den" building was said to be 2 MW of IT power while CB-1 would be 16 MW. This is roughly consistent with 22.5 MW of total facility power. This building is leased to Core42, a subsidiary of UAE-based G42. It likely uses NVIDIA DGX B200 servers.19 MW
Oct 1, 2024Land clearing begins for Building 1, also known as CB-1, the first large AI/HPC building on the site.–

How much power does Core42 Lake Mariner use?

About 58 MW as of Jul 23, 2026, by Epoch AI's estimate of the whole facility's draw. Running all year, 58 MW would use about 0.5 TWh.

Who owns Core42 Lake Mariner?

Core42; used by G42 (likely). Investors: Google. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Core42 Lake Mariner?

In Niagara County, the average customer is without power about 3.1 hours in a typical year in this site's outage record, with 4 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Core42 Lake Mariner?

8 plants within 15 miles total about 250 MW; the largest is Lockport Energy Associates (221 MW, natural gas), 14.8 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.