Data centers · every state

Every data center in America

2,955 operating data center sites, 930 more planned or under construction, and 77 frontier AI campuses that alone draw about 12.6 GW today and plan for 43.4 GW. Where they are, who runs them, what they draw, and the power prices and outage record around them.

Operating sites2,955In 51 states, 506 counties
In the pipeline930259 under construction, 671 planned
AI power today12.6 GW77 AI campuses, 6.0 GW a year ago
AI power planned43.4 GWEach campus at its planned peak

The map

Where the data centers are

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI) Under construction Planned

Diamonds are projects in development. Where a project gives no location it sits at the centre of its city or county.

AI campuses

The biggest AI data centers

Power is the whole facility's draw estimated by Epoch AI from satellite images, permits and filings. "Planned" is the highest point in its build timeline. Sort by any column.

CampusOwnerWhereNowPlannedFirst power
Anthropic-Amazon New Carlisle Amazon New Carlisle, IN 1.0 GW 2.3 GW June 2025
Colossus 2 SpaceXAI Memphis, TN 946 MW 2.1 GW October 2025
OpenAI Stargate Abilene Oracle Abilene, TX 824 MW 1.2 GW September 2025
Microsoft Fairwater Atlanta Microsoft Fayetteville, GA 636 MW 859 MW October 2025
Meta Prometheus Meta New Albany, OH 471 MW 1.3 GW October 2025
Microsoft Fairwater Wisconsin Microsoft Mount Pleasant, WI 369 MW 2.7 GW April 2026
Google Pryor (North) Google Pryor, OK 368 MW 442 MW July 2024
Colossus 1 SpaceXAI Memphis, TN 340 MW 442 MW August 2024
Google New Albany Google New Albany, OH 333 MW 400 MW April 2024
Google Columbus Google Columbus, OH 303 MW 464 MW April 2024
Amazon Madison Mega Site Amazon Canton, MS 284 MW 819 MW June 2025
CoreWeave Denton TX CoreWeave Denton, TX 262 MW 395 MW May 2025
QTS Richmond 1 – Sandston, VA 238 MW 333 MW January 2024
Google Bristow Google Bristow, VA 238 MW 286 MW April 2024
Google Omaha Google Omaha, NE 237 MW 474 MW April 2024

The build-out

How fast AI power is growing

0 MW10 GW20 GW30 GW40 GW50 GW20232024202520262027202820292030Today
Power drawn by the 77 US AI campuses Epoch AI tracks, by month. Solid: dated observations. Hatched: Epoch's projections from each campus's build plans.
0 MW10 GW20 GW30 GW40 GW50 GW2024202620282030Today
Power drawn by the 77 US AI campuses Epoch AI tracks, by month. Solid: dated observations. Hatched: Epoch's projections from each campus's build plans.

The pipeline

The biggest projects on the way

Planned and under-construction projects that publish a size, from Civic Returns, Server Country, AI GridWatch, Megawattlas and the operators' own lists (AI campuses Epoch AI tracks are above). Size is the developer's announced figure, often a full build-out over many years, and not every announced project gets built.

ProjectDeveloperStateStatusAnnounced size
New Era Energy Lea County AI Hub New Era Energy & Digital NM Planned 7.0 GW
Homer City Energy Campus Homer City Redevelopment PA Planned 4.5 GW
High Performance Compute Data Center Campus Joule Capital Partners UT Under construction 4.0 GW
DCIP DeSoto County AI Data Center DCIP Group FL Planned 4.0 GW
Project Camellia (OpenAI) OpenAI GA Planned 3.2 GW
Sailfish Comanche Circle Sailfish Digital Ventures TX Planned 3.2 GW
TECfusions Keystone Connect TECfusions PA Planned 3.0 GW
Crusoe WY Campus Tallgrass (Project Jade; Crusoe exited Jun 2026) WY Planned 2.7 GW
North Creek Tech Campus Amazon VA Planned 2.7 GW
Shippingport Power Station and Data Center Frontier Group of Companies PA Planned 2.7 GW
Adams Fork Data Center Energy Campus - Harless Site TransGas Development Systems LLC WV Planned 2.4 GW
Amazon Web Services (AWS) Hobart Tech Park Amazon Web Services IN Planned 2.4 GW
Mason County Technology Campus Fortune 100 Company (undisclosed) KY Planned 2.2 GW
Birchwood AWS Amazon VA Planned 2.2 GW
George Washington Village Data Center Garrett Development Corporation VA Planned 2.1 GW

Cancelled

Projects that were dropped

109 projects recorded as cancelled or withdrawn, often after local opposition, a zoning vote or a developer pulling out.

ProjectDeveloperStateAnnounced size
Socorro Green Data Campus Green Data NM 2.0 GW
QTS Wisconsin QTS WI 1.6 GW
A1 Data Center (Millville) – NJ 1.4 GW
Stillwater data center campus (Panhandle Road) – GA 1.3 GW
Rocklocker Kalkaska County Data Center Rocklocker LLC MI 1.0 GW
Sansone York Township Toyota Land Data Center Sansone Group MI 1.0 GW
Sentinel Grove Technology Park (Project Jarvis) Epic Estates 68 LLC FL 1.0 GW
Kingsboro Data Center Campus Energy Storage Solutions NC 900 MW
Prologis 32 Mile Technical Campus Prologis MI 800 MW
Project Cardinal Data Center TAC Data Centers MT 600 MW
Project Tango PBA Holdings FL 600 MW
Pennhurst Data Center Penn Hurst Holdings DE LLC PA 550 MW

By state

Data centers by state

Household price: the average residential cents per kWh in 2025 and the change since 2018 (EIA-861). It sits beside the data centers for context; prices move with fuel costs, storms and wires spending too.

StateSitesBeing builtPlannedLocal bansAI campusesAI power nowAI plannedHome priceSince 2018
Virginia 435 26 121 11 7 1.0 GW 2.0 GW 15.3¢ +30%
Texas 406 56 65 10 14 1.7 GW 8.9 GW 15.4¢ +38%
California 236 10 12 21 – – – 31.4¢ +66%
Oregon 147 3 6 3 2 334 MW 428 MW 15.5¢ +41%
Ohio 130 16 22 55 7 1.5 GW 3.6 GW 16.9¢ +35%
Arizona 110 9 17 2 3 449 MW 767 MW 15.3¢ +20%
Illinois 107 12 22 14 – – – 17.7¢ +38%
Georgia 103 14 69 32 3 681 MW 923 MW 14.7¢ +29%
New Jersey 93 3 6 73 1 50 MW 70 MW 22.5¢ +46%
Washington 90 5 5 19 – – – 13.2¢ +35%
Iowa 79 2 14 16 4 427 MW 2.4 GW 13.6¢ +11%
Pennsylvania 73 2 44 11 2 108 MW 336 MW 19.3¢ +39%
New York 67 2 17 13 2 268 MW 499 MW 26.4¢ +42%
Colorado 65 4 5 13 – – – 15.7¢ +29%
Florida 65 3 12 26 – – – 15.2¢ +32%
North Carolina 61 6 12 38 1 65 MW 91 MW 14.0¢ +26%
Nevada 50 5 9 8 1 161 MW 389 MW 13.3¢ +12%
Missouri 48 5 10 17 1 105 MW 126 MW 13.3¢ +17%
Minnesota 42 2 16 18 1 178 MW 241 MW 15.8¢ +20%
Utah 41 4 14 8 2 133 MW 590 MW 13.0¢ +25%
Indiana 39 7 23 21 3 1.2 GW 3.6 GW 16.0¢ +30%
Tennessee 39 4 5 25 3 1.4 GW 2.6 GW 13.2¢ +23%
Nebraska 36 2 1 16 4 695 MW 1.2 GW 12.1¢ +13%
Michigan 33 – 17 53 1 – 1.4 GW 20.0¢ +30%
Wyoming 30 1 4 – 1 152 MW 249 MW 13.4¢ +18%
Massachusetts 29 – 3 6 – – – 30.4¢ +41%
New Mexico 28 1 3 4 2 118 MW 2.7 GW 14.8¢ +17%
Maryland 26 3 9 19 – – – 19.5¢ +47%
Mississippi 23 5 4 1 2 512 MW 1.8 GW 14.0¢ +26%
Alabama 23 6 10 14 2 299 MW 663 MW 16.1¢ +32%
Oklahoma 23 8 9 13 2 368 MW 623 MW 13.2¢ +28%
North Dakota 19 1 8 1 1 68 MW 520 MW 11.8¢ +15%
Kentucky 19 3 8 28 – – – 13.1¢ +24%
Wisconsin 18 3 8 33 2 369 MW 4.0 GW 18.1¢ +29%
South Carolina 17 8 5 10 1 129 MW 168 MW 15.1¢ +22%
Louisiana 14 4 1 1 1 – 2.2 GW 12.5¢ +31%
Kansas 14 2 12 13 – – – 14.4¢ +8%
Montana 12 – 2 3 – – – 13.0¢ +19%
Arkansas 10 4 2 6 – – – 12.9¢ +31%
Connecticut 9 – 10 3 – – – 29.3¢ +38%
Idaho 8 2 2 3 1 152 MW 198 MW 11.8¢ +17%
New Hampshire 7 – 1 3 – – – 24.5¢ +25%
Hawaii 6 3 1 – – – – 40.4¢ +24%
South Dakota 6 – 3 2 – – – 13.3¢ +15%
Delaware 5 – 3 2 – – – 17.1¢ +37%
Maine 4 – 5 9 – – – 27.7¢ +64%
West Virginia 4 3 7 – – – – 15.4¢ +38%
District of Columbia 2 – – – – – – 21.9¢ +71%
Rhode Island 2 – 1 3 – – – 29.5¢ +43%
Vermont 2 – – 3 – – – 22.8¢ +26%
Alaska 0 – 6 1 – – – 26.1¢ +19%

By county

The data center counties

Hours without power: the average customer's hours out in a typical year in this site's outage record (ORNL EAGLE-I).

Operators

Who runs them

Operators as tagged in OpenStreetMap or named by Civic Returns (1,874 of 2,955 sites name one), with spellings merged.

OperatorMapped sites
Amazon Web Services260
Cogent Communications143
Digital Realty90
Microsoft78
QTS68
Google64
Meta64
Equinix63
DataBank62
Lumen58
CyrusOne56
Flexential48
Centersquare37
CoreSite36
EdgeConneX35
TierPoint32
NTT30
STACK Infrastructure30
Vantage26
H5 Data Centers24

Local pushback

Bans and moratoriums

704 local and state moratoriums or bans on data centers are recorded as enacted in 47 states, 89 more are proposed or under review, and 94 have expired, been rejected or been lifted (AI GridWatch, as of Nov 16, 2026). A time-limited moratorium with no documented end date keeps showing as enacted, and many are extended, so check with the town or county before relying on one.

WhereLevelStatusDateRuns
Bucksport, ME Local Enacted Oct 8, 2026 A stated duration, but the end date isn't recorded here
Easthampton, MA Local Enacted Oct 7, 2026 Term not documented
Grand Junction, CO Local Proposed Oct 7, 2026 Runs until a condition is met, not to a date
Raleigh, NC Local Enacted Oct 6, 2026 to Apr 6, 2027
Charleston, IL Local Enacted Oct 6, 2026 to Oct 6, 2027
San Francisco, CA Local Enacted Oct 6, 2026 A stated duration, but the end date isn't recorded here
Oakland, CA Local Enacted Oct 6, 2026 A stated duration, but the end date isn't recorded here
Humboldt County, CA County Enacted Oct 6, 2026 A stated duration, but the end date isn't recorded here
Menasha, WI Local Enacted Oct 5, 2026 A stated duration, but the end date isn't recorded here
Delphos, OH Local Enacted Oct 5, 2026 A stated duration, but the end date isn't recorded here
West Seneca, NY Local Enacted Oct 5, 2026 A stated duration, but the end date isn't recorded here
Beaufort County, NC Local Enacted Oct 5, 2026 A stated duration, but the end date isn't recorded here

How complete

Our count beside other trackers

No agency counts data centers, so every tracker differs in what it counts. Pew Research counted 3,068 operating US data centers in Data Center Map's listings (February 2026; states shown are Pew's top 15). The US Data Center Map (dcmap.us) counts 4,771 operating, under-construction and planned sites (October 2026). This map has 2,955 operating or permitted sites and 3,885 counting projects in development. Commercial directories list single colocation suites and small enterprise server rooms that public records and maps rarely show.

StateOurs, operatingPew / Data Center Map, operatingOurs, with projectsdcmap.us, with projects
Virginia 435 398 582 591
Texas 406 296 527 561
California 236 277 258 343
Ohio 130 166 168 238
Georgia 103 94 186 232
Arizona 110 98 136 176
New York 67 148 86 168
Illinois 107 139 141 164
Florida 65 120 80 141
Pennsylvania 73 78 119 132
Washington 90 124 100 117
Indiana 39 38 69 106
New Jersey 93 – 102 103
Oregon 147 115 156 101
North Carolina 61 72 79 99

Their figures: Pew Research Center from Data Center Map; US Data Center Map, data as of Oct 2026. Quoted, not copied: their site lists are not used here.

How many data centers are in the US?

This map has 2,955 operating or permitted data center sites in 51 states: 1,743 from OpenStreetMap (read Nov 17, 2026; buildings inside a mapped campus count with it), 461 from data center operators' own published facility lists, 492 from EPA facility records (most hold air permits for their backup generators), 185 from the Civic Returns dataset, and 73 from named map features, Overture Maps places, Wikidata and EIA power plant records, each kept only when it is not already on the map. There is no official count. Pew Research's count of one commercial directory (Data Center Map, February 2026) found about 3,000 operating facilities, a list that also takes in small colocation suites, so treat this map as most of the large sites rather than every server room.

How many data centers are being built?

259 projects are under construction and 671 more are planned or announced in the Civic Returns and Server Country databases, on top of the AI campuses Epoch AI tracks. 450 of them publish a size, adding up to about 215.4 GW; announced sizes are often a campus's full build-out over many years. 109 projects have been cancelled or withdrawn.

How much electricity do data centers use?

About 176 TWh in 2023, or 4.4% of all US electricity, by Lawrence Berkeley National Laboratory's 2024 report to Congress, up from 58 TWh in 2014. Its scenarios put 2028 at 325 to 580 TWh, 6.7% to 12% of the country's electricity.

Which state has the most data centers?

Virginia, with 435 mapped sites, followed by Texas (406), California (236), Oregon (147). Loudoun County, VA alone has 209.

What is the largest AI data center in the US?

By power drawn today, Anthropic-Amazon New Carlisle (Amazon) in New Carlisle, IN, at about 1.0 GW by Epoch AI's estimate. By planned size, Microsoft Fairwater Wisconsin in Mount Pleasant, WI, planned to reach about 2.7 GW by May 2028.

How much power do AI data centers use?

The 77 US AI campuses Epoch AI tracks draw about 12.6 GW between them today, up from 6.0 GW a year earlier. Their build plans add up to about 43.4 GW by January 2030. For scale, 1.0 GW running all year uses about 8.8 TWh, roughly what 800,000 US homes use.

Do data centers cause power outages?

Not in this record: outages come overwhelmingly from storms and damage to local wires. 8 of the 10 counties with the most mapped data centers have fewer hours without power a year than the median US county (6.5 h); Loudoun County averages 2.6 h. The open question is cost and supply: grid operators and utilities are building plants and lines for this demand, and who pays for them is being argued before state regulators. The state table below puts each state's household electricity price beside its data centers; it shows the two side by side and does not show that one causes the other.

Sources: 461 sites from data center operators' own published facility lists (facility name and address, read from each operator's website). EPA ECHO facility records (public domain): 492 sites whose industry code is data processing and hosting or whose name names a data center or data center operator, each checked by name; these include sites permitted but not yet finished. Overture Maps places (CDLA-Permissive-2.0), Wikidata (CC0) and EIA-860. Operating sites from OpenStreetMap © OpenStreetMap contributors (ODbL 1.0), read Nov 17, 2026, processed the way Pacific Northwest National Laboratory's IM3 Open Source Data Center Atlas does: buildings and points inside a mapped campus count with that campus, and each site is placed in a county by its centre. 185 operating sites and 465 projects from Civic Returns, US Data Centers & Community Benefits Dataset (CC BY 4.0, audited to Oct 18, 2026); its operating sites within half a mile of an OpenStreetMap site are left out as likely the same. 449 further projects from the Server Country project database (CC BY 4.0, snapshot Oct 2, 2026) where they match nothing in Civic Returns; they have no coordinates and sit at their city or county. AI campuses from Epoch AI, "AI data centers" (CC BY 4.0), as of Nov 17, 2026, placed by address (Census geocoder or OpenStreetMap Nominatim) or, where there is none, their city; projects Epoch tracks are counted only there. Moratoriums and further projects: AI GridWatch (CC BY 4.0) and Megawattlas (CC BY 4.0), matched against the other lists. National electricity use: LBNL, 2024 United States Data Center Energy Usage Report. Electricity prices: EIA-861. Outage hours: ORNL EAGLE-I. See also surging demand, power plants and electric bills.