AI data center · Huntsville, Alabama

Meta Huntsville

Meta's AI campus in Madison County. It draws about 146 MW today and is planned to reach 198 MW by June 2026.

Power now146 MWAs of Jun 2, 2026
Planned peak198 MWJune 2026
Compute167kH100-equivalent chips now
Capital cost$5.5BSo far, 2025 dollars

Latest look · Jun 2, 2026

What the satellite shows

We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines.

Build-out

Power, month by month

0 MW50 MW100 MW150 MW200 MW250 MW20222023202420252026
Power drawn by Meta Huntsville, from Epoch AI's dated observations.
0 MW50 MW100 MW150 MW200 MW250 MW20222023202420252026
Power drawn by Meta Huntsville, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Meta
Used by
Meta
Energy companies
Tennessee Valley Authority, NextEra Energy Resources, First Solar
Chips
B300
Address
5400 Prosperity Dr NW, Toney, AL
County
Madison County (approximate)

Where

On the map of Alabama

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Huntsville, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
TAI Huntsville Solar Hybrid● Solar32 MW9.5 mi
Redstone Arsenal Hybrid● Solar11 MW7 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jun 2, 2026We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines.198 MW
Mar 4, 2026We estimate that Building 1 is operational 30 days after the appearance of color artifacts on the fans.105 MW
Feb 2, 2026Color artifacts appear on small number of Building 1 fans. Continued presence of construction equipment and unfinished land around Building 2 suggests the final phase of construction.–
Nov 4, 2025We believe Building 1 and 2 are still being finished due to continued construction vehicles and unfinished land around the data center sites.–
Mar 3, 2025Building 2 roof starts to go on and its cooling installation is in progress.–
Dec 13, 2021Building 1 land clearing begins.–

How much power does Meta Huntsville use?

About 146 MW as of Jun 2, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 198 MW in its build plans by June 2026. Running all year, 146 MW would use about 1.3 TWh.

Who owns Meta Huntsville?

Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Meta Huntsville?

In Madison County, the average customer is without power about 2.2 hours in a typical year in this site's outage record, with 4 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Meta Huntsville?

2 plants within 15 miles total about 43 MW; the largest is TAI Huntsville Solar Hybrid (32 MW, solar), 9.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.