AI data center · Huntsville, Alabama
Meta Huntsville
Meta's AI campus in Madison County. It draws about 146 MW today and is planned to reach 198 MW by June 2026.
Latest look · Jun 2, 2026
What the satellite shows
We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Meta
- Used by
- Meta
- Energy companies
- Tennessee Valley Authority, NextEra Energy Resources, First Solar
- Chips
- B300
- Address
- 5400 Prosperity Dr NW, Toney, AL
- County
- Madison County (approximate)
Where
On the map of Alabama
Placed at the centre of Huntsville, as no address could be matched, so the dot and the county are approximate.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| TAI Huntsville Solar Hybrid | ● Solar | 32 MW | 9.5 mi |
| Redstone Arsenal Hybrid | ● Solar | 11 MW | 7 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jun 2, 2026 | We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines. | 198 MW |
| Mar 4, 2026 | We estimate that Building 1 is operational 30 days after the appearance of color artifacts on the fans. | 105 MW |
| Feb 2, 2026 | Color artifacts appear on small number of Building 1 fans. Continued presence of construction equipment and unfinished land around Building 2 suggests the final phase of construction. | – |
| Nov 4, 2025 | We believe Building 1 and 2 are still being finished due to continued construction vehicles and unfinished land around the data center sites. | – |
| Mar 3, 2025 | Building 2 roof starts to go on and its cooling installation is in progress. | – |
| Dec 13, 2021 | Building 1 land clearing begins. | – |
How much power does Meta Huntsville use?
About 146 MW as of Jun 2, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 198 MW in its build plans by June 2026. Running all year, 146 MW would use about 1.3 TWh.
Who owns Meta Huntsville?
Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Meta Huntsville?
In Madison County, the average customer is without power about 2.2 hours in a typical year in this site's outage record, with 4 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Meta Huntsville?
2 plants within 15 miles total about 43 MW; the largest is TAI Huntsville Solar Hybrid (32 MW, solar), 9.5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.