Data centers · Alabama
Data centers in Alabama
23 operating data center sites, 16 projects planned or under construction and 2 AI campuses planned to draw 663 MW.
The map
Every mapped site
AI campuses
Alabama's AI data centers
| Campus | Owner | Where | Now | Planned |
|---|---|---|---|---|
| Meta Montgomery | Meta | Montgomery County | 153 MW | 465 MW |
| Meta Huntsville | Meta | Madison County | 146 MW | 198 MW |
The pipeline
Projects on the way
From Civic Returns, Server Country, AI GridWatch, Megawattlas and the operators' own lists. Size is the developer's announced figure, often a full build-out over years. Projects with no published location are mapped at their city or county.
Local pushback
Bans and moratoriums
14 recorded as enacted, 0 proposed or under review, 2 expired, rejected or lifted (AI GridWatch). A time-limited moratorium with no documented end date keeps showing as enacted; check with the town or county.
| Where | Level | Status | Date | Runs |
|---|---|---|---|---|
| Baldwin County · Baldwin | Local | Enacted | Oct 1, 2026 | A stated duration, but the end date isn't recorded here |
| Foley · Baldwin | City | Enacted | Sep 8, 2026 | to Mar 8, 2027 |
| Tarrant · Jefferson | City | Enacted | Sep 8, 2026 | to Sep 8, 2027 |
| Lowndes County · Lowndes | County | Expired | Aug 26, 2026 | to Oct 25, 2026 |
| Westover · Shelby | City | Enacted | Aug 18, 2026 | to Feb 18, 2027 |
| Anniston · Calhoun | City | Enacted | Aug 18, 2026 | to Aug 18, 2027 |
| Pinson · Jefferson | Local | Enacted | Aug 7, 2026 | to Aug 7, 2027 |
| Harpersville · Shelby | City | Enacted | Aug 3, 2026 | to Feb 3, 2027 |
| Springville · St. Clair | Local | Enacted | Jul 6, 2026 | to Jul 6, 2027 |
| Fairfield · Jefferson | Local | Enacted | Jul 1, 2026 | Term not documented |
| Cullman · Cullman | Local | Enacted | Jun 24, 2026 | to Jun 24, 2027 |
| Homewood · Jefferson | Local | Enacted | Jun 22, 2026 | to Jun 22, 2027 |
| Fort Payne · DeKalb | Local | Enacted | Jun 16, 2026 | to Dec 16, 2026 |
| Leeds · Jefferson | Local | Enacted | Jun 3, 2026 | to Jun 3, 2027 |
| Birmingham · Jefferson | Local | Expired | Mar 3, 2026 | to Sep 3, 2026 |
| Prichard · Mobile | Local | Enacted | Jan 1, 2026 | to Feb 4, 2027 |
By county
Where the data centers cluster
| County | Mapped sites | Hours without power a year |
|---|---|---|
| Madison County | 11 | 2.2 h |
| Jefferson County | 4 | 5.4 h |
| Montgomery County | 2 | 3.9 h |
| Jackson County | 1 | 0.1 h |
| Houston County | 1 | 3.6 h |
| Mobile County | 1 | 20 h |
| Escambia County | 1 | 6.4 h |
| Lee County | 1 | 3.3 h |
| Talladega County | 1 | 11 h |
Every named site
The list
21 of 23 operating sites carry a name or operator; the rest are on the map above only. Area is the mapped outline (land for a campus, roof for a building).
| Site | Operator | County | Source | Acres |
|---|---|---|---|---|
| Google Jackson County Data Center | Jackson | Campus, 2 buildings | 173 | |
| Meta Huntsville Data center | Meta | Madison | Building | 20 |
| Sungard Systems International | – | Jefferson | Campus | 15 |
| Meta Huntsville Data center | Meta | Madison | Building | 13 |
| Meta Huntsville Data center | Meta | Madison | Building | 8.1 |
| DC BLOX BHM1-A | – | Jefferson | Building | 0.6 |
| SimpleHelix | – | Madison | Building | 0.4 |
| George C. Wallace Alabama Supercomputer Center | – | Madison | Building | 0.3 |
| AngelTrax Data Center | AngelTrax Mobile Video Surveillance Solutions | Houston | Building | 0.2 |
| DC Blox - Huntville Data Center | DC Blox | Madison | Civic Returns | 0.2 |
| Cogent Mobile Edge Data Center | Cogent Communications | Mobile | Operator's own list | – |
| Cogent Huntsville Edge Data Center | Cogent Communications | Madison | Operator's own list | – |
| Cogent Montgomery Edge Data Center | Cogent Communications | Montgomery | Operator's own list | – |
| Cogent Birmingham Edge Data Center | Cogent Communications | Jefferson | Operator's own list | – |
| Cogent Atmore Edge Data Center | Cogent Communications | Escambia | Operator's own list | – |
| Core Scientific Auburn 1 | Core Scientific | Lee | Operator's own list | – |
| DC BLOX Huntsville | DC BLOX | Madison | Operator's own list | – |
| Meta Huntsville Data Center | Meta | Madison | Operator's own list | – |
| Blue Cross And Blue Shield Of Alabama Data Center | – | Jefferson | EPA record | – |
| Childersburg Data Center | – | Talladega | EPA record | – |
| Oppidan Data Center - Mgm | – | Montgomery | EPA record | – |
How many data centers are in Alabama?
23 operating or permitted sites on this map, from OpenStreetMap, EPA facility records and other open sources: the 30th most of any state. 2 are mapped as whole campuses. The map covers most large sites, not every server room, so the true number is higher.
How many data centers are being built in Alabama?
6 under construction and 10 planned or announced in the Civic Returns and Server Country databases; the 9 that publish a size add up to about 2.4 GW, besides 2 AI campuses tracked by Epoch AI. 1 project has been cancelled.
Which Alabama county has the most data centers?
Madison County, with 11 operating sites, then Jefferson County (4) and Montgomery County (2).
Who operates data centers in Alabama?
Among sites that name an operator: Cogent Communications (5), Meta (4), Google (1), AngelTrax Mobile Video Surveillance Solutions (1), DC Blox (1).
What AI data centers are in Alabama?
Meta Montgomery in Montgomery (153 MW now, 465 MW planned); Meta Huntsville in Huntsville (146 MW now, 198 MW planned), by Epoch AI's estimates.
What do Alabama households pay for electricity?
16.1¢ per kWh on average in 2025 (US: 17.2¢), up 32% since 2018, from EIA-861. Prices move with fuel, storms and wires spending as well as new demand.
Sources: operating sites from OpenStreetMap © OpenStreetMap contributors (ODbL 1.0), read Nov 17, 2026; operators' own published facility lists; EPA ECHO facility records (public domain); Civic Returns, US Data Centers & Community Benefits Dataset (CC BY 4.0); Overture Maps places (CDLA-Permissive-2.0); Wikidata (CC0); EIA-860. Projects in development from Civic Returns, the Server Country project database, AI GridWatch and Megawattlas (all CC BY 4.0). Moratoriums from AI GridWatch (CC BY 4.0). AI campuses from Epoch AI, "AI data centers", CC BY 4.0. Electricity prices: EIA-861. Outage hours: ORNL EAGLE-I. How this is counted.