Meta Montgomery

Meta's AI campus in Montgomery County. It draws about 153 MW today and is planned to reach 465 MW by February 2027.

Power now153 MWAs of Jun 18, 2026
Planned peak465 MWFebruary 2027
Compute175kH100-equivalent chips now
Capital cost$5.8BSo far, 2025 dollars

Latest look · Jun 18, 2026

What the satellite shows

We estimate Buildings 1 and 2 are operational.

Build-out

Power, month by month

0 MW200 MW400 MW600 MW202520262027Today
Power drawn by Meta Montgomery, from Epoch AI's dated observations and (hatched) its projections.
0 MW200 MW400 MW600 MW202520262027Today
Power drawn by Meta Montgomery, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Meta
Used by
Meta
Built by
Hensel Phelps
Chips
B300
Water use
0.00 million gallons a day (Epoch AI estimate)
Address
Co Rd 42, Montgomery, AL 36105, USA
County
Montgomery County

Where

On the map of Alabama

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
E B Harris Electric Generating Plant● Natural gas1.30 GW14.7 mi
Black Bear Solar 1● Solar100 MW5.2 mi
General Electric Plastic● Natural gas97 MW10 mi
International Paper Prattville Mill● Biomass90 MW12.4 mi
Old Hayneville Solar, LLC● Solar80 MW4.6 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jun 18, 2026We estimate Buildings 1 and 2 are operational.199 MW
Mar 20, 2026Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server installation. Building 3 has a half-finished roof and Building 4 shell is beginning construction. Buildings 5 and 6 are under construction.–
Jul 4, 2025Building 1 and 2 under construction, with all chillers visible.–
Mar 1, 2024Land clearing begins.–

Plus 2 projected steps to February 2027, from Epoch AI's reading of the build plans.

How much power does Meta Montgomery use?

About 153 MW as of Jun 18, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 465 MW in its build plans by February 2027. Running all year, 153 MW would use about 1.3 TWh.

Who owns Meta Montgomery?

Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Meta Montgomery?

In Montgomery County, the average customer is without power about 3.9 hours in a typical year in this site's outage record, with 6 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Meta Montgomery?

5 plants within 15 miles total about 1.67 GW; the largest is E B Harris Electric Generating Plant (1.30 GW, natural gas), 14.7 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus