AI data center · Goodyear, Arizona
Microsoft Goodyear
Microsoft's AI campus in Maricopa County. It draws about 202 MW today and is planned to reach 263 MW by September 2025.
Latest look · Apr 27, 2026
What the satellite shows
Foundations appear to be underway for Building 5 and 6, just north of Building 4.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Microsoft
- Used by
- OpenAI (likely), Microsoft
- Chips
- H100, B200
- Address
- 14250 W Broadway Rd, Goodyear, AZ 85338
- County
- Maricopa County
Where
On the map of Arizona
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| West Phoenix | ● Natural gas | 1.21 GW | 12.1 mi |
| Agua Fria | ● Natural gas | 738 MW | 13.3 mi |
| Sierra Estrella Energy Storage | ● Storage | 250 MW | 2.9 mi |
| Justice Energy Storage | ● Storage | 150 MW | 7.5 mi |
| Pluto Energy Storage | ● Storage | 75 MW | 2.7 mi |
| El Sol BESS | ● Storage | 50 MW | 11.5 mi |
| Luke Solar | ● Solar | 11 MW | 8.1 mi |
| Buckeye Union HS District 201 | ● Solar | 3 MW | 12.2 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Apr 27, 2026 | Foundations appear to be underway for Building 5 and 6, just north of Building 4. | 263 MW |
| Nov 12, 2025 | Confirmation that Building 3 and 4 look complete. | 263 MW |
| Sep 1, 2025 | Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth. | 263 MW |
| Jan 16, 2025 | Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth. | 105 MW |
| Apr 24, 2023 | Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth. | 53 MW |
| Jun 21, 2021 | Land clearing begins for Building 1. | – |
How much power does Microsoft Goodyear use?
About 202 MW as of Apr 27, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 263 MW in its build plans by September 2025. Running all year, 202 MW would use about 1.8 TWh.
Who owns Microsoft Goodyear?
Microsoft; used by OpenAI (likely), Microsoft. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Microsoft Goodyear?
In Maricopa County, the average customer is without power about 1.5 hours in a typical year in this site's outage record, with 3 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Microsoft Goodyear?
8 plants within 15 miles total about 2.50 GW; the largest is West Phoenix (1.21 GW, natural gas), 12.1 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.