AI data center · Goodyear, Arizona

Microsoft Goodyear

Microsoft's AI campus in Maricopa County. It draws about 202 MW today and is planned to reach 263 MW by September 2025.

Power now202 MWAs of Apr 27, 2026
Planned peak263 MWSeptember 2025
Compute205kH100-equivalent chips now
Capital cost$7.7BSo far, 2025 dollars

Latest look · Apr 27, 2026

What the satellite shows

Foundations appear to be underway for Building 5 and 6, just north of Building 4.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW20222023202420252026
Power drawn by Microsoft Goodyear, from Epoch AI's dated observations.
0 MW100 MW200 MW300 MW20222023202420252026
Power drawn by Microsoft Goodyear, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Microsoft
Used by
OpenAI (likely), Microsoft
Chips
H100, B200
Address
14250 W Broadway Rd, Goodyear, AZ 85338
County
Maricopa County

Where

On the map of Arizona

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
West Phoenix● Natural gas1.21 GW12.1 mi
Agua Fria● Natural gas738 MW13.3 mi
Sierra Estrella Energy Storage● Storage250 MW2.9 mi
Justice Energy Storage● Storage150 MW7.5 mi
Pluto Energy Storage● Storage75 MW2.7 mi
El Sol BESS● Storage50 MW11.5 mi
Luke Solar● Solar11 MW8.1 mi
Buckeye Union HS District 201● Solar3 MW12.2 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Apr 27, 2026Foundations appear to be underway for Building 5 and 6, just north of Building 4.263 MW
Nov 12, 2025Confirmation that Building 3 and 4 look complete.263 MW
Sep 1, 2025Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.263 MW
Jan 16, 2025Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.105 MW
Apr 24, 2023Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.53 MW
Jun 21, 2021Land clearing begins for Building 1.–

How much power does Microsoft Goodyear use?

About 202 MW as of Apr 27, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 263 MW in its build plans by September 2025. Running all year, 202 MW would use about 1.8 TWh.

Who owns Microsoft Goodyear?

Microsoft; used by OpenAI (likely), Microsoft. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Microsoft Goodyear?

In Maricopa County, the average customer is without power about 1.5 hours in a typical year in this site's outage record, with 3 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Microsoft Goodyear?

8 plants within 15 miles total about 2.50 GW; the largest is West Phoenix (1.21 GW, natural gas), 12.1 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.