AI data center · Mesa, Arizona
Google Mesa
Google's AI campus in Maricopa County. It draws about 183 MW today and is planned to reach 237 MW by August 2026.
Latest look · Aug 15, 2026
What the satellite shows
Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Chips
- TPU v6e, TPU v5p
- County
- Maricopa County (approximate)
Where
On the map of Arizona
Placed at the centre of Mesa, as no address could be matched, so the dot and the county are approximate.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Santan | ● Natural gas | 1.33 GW | 5 mi |
| Ocotillo | ● Natural gas | 806 MW | 11.4 mi |
| Kyrene | ● Natural gas | 596 MW | 13 mi |
| Pediment BESS I | ● Storage | 250 MW | 7.2 mi |
| Superstition Energy Storage | ● Storage | 90 MW | 7.2 mi |
| Queen Creek Solar Farm | ● Solar | 19 MW | 10.9 mi |
| Arizona State University CHP | ● Natural gas | 17 MW | 12.3 mi |
| AES ES GILBERT | ● Storage | 10 MW | 14.2 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Aug 15, 2026 | Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026. | 237 MW |
| May 15, 2026 | Building 2 is close to being operational. There is only construction left on the backup generators, which are almost complete. Some equipment is also strewn around the building, especially near the air-cooled chillers. Preparation seems to have begun for Building 3 at the site. | 126 MW |
| Sep 7, 2025 | Building 2 roof is mostly completed. Building 2's backup generators are almost complete, and cooling is a little more than halfway complete. The Building 2 substation is also under construction. | 126 MW |
| Jul 1, 2025 | Building 1 is operational. This is based on the state of construction on 2025-03-02 as seen on Google Earth, where building shell and external components seems to have been completed, but there is still a lot of construction equipment present. That equipment appears to have been cleared up by this date, 4 months later, with the 2025-09-07 satellite imagery providing an upper bound. Construction has begun on the Building 2 roof, with work beginning on the areas for cooling and generators as well. | 126 MW |
| Aug 1, 2023 | Land clearing begins for the entire site. | – |
How much power does Google Mesa use?
About 183 MW as of Aug 15, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 237 MW in its build plans by August 2026. Running all year, 183 MW would use about 1.6 TWh.
Who owns Google Mesa?
Google. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google Mesa?
In Maricopa County, the average customer is without power about 1.5 hours in a typical year in this site's outage record, with 3 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google Mesa?
8 plants within 15 miles total about 3.13 GW; the largest is Santan (1.33 GW, natural gas), 5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.