AI data center · Mesa, Arizona

Google Mesa

Google's AI campus in Maricopa County. It draws about 183 MW today and is planned to reach 237 MW by August 2026.

Power now183 MWAs of Aug 15, 2026
Planned peak237 MWAugust 2026
Compute290kH100-equivalent chips now
Capital cost$6.9BSo far, 2025 dollars

Latest look · Aug 15, 2026

What the satellite shows

Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW202420252026
Power drawn by Google Mesa, from Epoch AI's dated observations.
0 MW100 MW200 MW300 MW202420252026
Power drawn by Google Mesa, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Google
Chips
TPU v6e, TPU v5p
County
Maricopa County (approximate)

Where

On the map of Arizona

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Mesa, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Santan● Natural gas1.33 GW5 mi
Ocotillo● Natural gas806 MW11.4 mi
Kyrene● Natural gas596 MW13 mi
Pediment BESS I● Storage250 MW7.2 mi
Superstition Energy Storage● Storage90 MW7.2 mi
Queen Creek Solar Farm● Solar19 MW10.9 mi
Arizona State University CHP● Natural gas17 MW12.3 mi
AES ES GILBERT● Storage10 MW14.2 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Aug 15, 2026Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.237 MW
May 15, 2026Building 2 is close to being operational. There is only construction left on the backup generators, which are almost complete. Some equipment is also strewn around the building, especially near the air-cooled chillers. Preparation seems to have begun for Building 3 at the site.126 MW
Sep 7, 2025Building 2 roof is mostly completed. Building 2's backup generators are almost complete, and cooling is a little more than halfway complete. The Building 2 substation is also under construction.126 MW
Jul 1, 2025Building 1 is operational. This is based on the state of construction on 2025-03-02 as seen on Google Earth, where building shell and external components seems to have been completed, but there is still a lot of construction equipment present. That equipment appears to have been cleared up by this date, 4 months later, with the 2025-09-07 satellite imagery providing an upper bound. Construction has begun on the Building 2 roof, with work beginning on the areas for cooling and generators as well.126 MW
Aug 1, 2023Land clearing begins for the entire site.–

How much power does Google Mesa use?

About 183 MW as of Aug 15, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 237 MW in its build plans by August 2026. Running all year, 183 MW would use about 1.6 TWh.

Who owns Google Mesa?

Google. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Mesa?

In Maricopa County, the average customer is without power about 1.5 hours in a typical year in this site's outage record, with 3 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google Mesa?

8 plants within 15 miles total about 3.13 GW; the largest is Santan (1.33 GW, natural gas), 5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.