Storage power plant · Maricopa, AZ
Pediment BESS I
Pediment BESS I is a 250 MW storage power plant in Maricopa County, Arizona, operated by Pediment BESS I LLC. Its oldest generator still running came online in 2026.
Pediment BESS I in context
Among the 41 storage plants in Arizona in the EIA's inventory, it is the 9th largest, about 4.0% of the state's 6.3 GW of storage capacity.
Maricopa County has 82 power plants of 1 MW or more with 24 GW in all; Pediment BESS I is 1% of that and the 6th largest of 21 storage plants there.
The average electricity customer in Maricopa County goes 1.5 hours a year without power, the 7th most of 11 counties in Arizona. The county's page has the full outage record.
Where it is
Pediment BESS I (outlined) and other plants in Maricopa County, shaded. 33.356, -111.602.
Plant facts
- Operator
- Pediment BESS I LLC
- Sector
- IPP Non-CHP
- Grid operator
- SRP
- County
- Maricopa County, AZ
- EIA plant ID
- 68477
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Batteries | 250 MW · 1,000 MWh | 2026 | – |
Questions
Pediment BESS I, answered
How much can Pediment BESS I store and deliver?
Pediment BESS I can deliver up to 250 MW and hold 1,000 MWh of energy, from one battery or storage system.
Where is Pediment BESS I?
Pediment BESS I is in Maricopa County, Arizona, at about 33.356°, -111.602°. It is one of 82 power plants of 1 MW or more in the county. The average electricity customer in Maricopa County goes 1.5 hours a year without power, the 7th most of 11 counties in Arizona. The county's page has the full outage record.
Who operates Pediment BESS I?
It is operated by Pediment BESS I LLC (EIA sector: IPP Non-CHP), and it feeds Salt River Project.
When did Pediment BESS I open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.