Red Hawk is a 1.1 GW natural gas power plant in Maricopa County, Arizona, operated by Arizona Public Service Co. Its oldest generator still running came online in 2002. In 2025 it generated 4.8 TWh, about what 392,000 average Arizona homes use in a year.

Capacity1.1 GWNameplate, September 2026
Generated4.8 TWhIn 2025
Capacity factor49%Share of the most it could make, 2025
Generators6Oldest from 2002

Red Hawk in context

Among the 33 natural gas plants in Arizona in the EIA's inventory, it is the 4th largest, about 6.2% of the state's 18 GW of natural gas capacity.

Maricopa County has 82 power plants of 1 MW or more with 24 GW in all; Red Hawk is 5% of that and the 4th largest of 15 natural gas plants there.

Its capacity factor of 49% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in Maricopa County goes 1.5 hours a year without power, the 7th most of 11 counties in Arizona. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02,0004,0006,0008,00020182019202020212022202320242025GWh 4,843
02,0004,0006,0008,00020192021202320254,843

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Red Hawk (outlined) and other plants in Maricopa County, shaded. 33.335, -112.841.

Plant facts

Operator
Arizona Public Service Co
Sector
Electric Utility
Grid operator
SRP
County
Maricopa County, AZ
EIA plant ID
55455
Where Arizona's power comes from → Arizona power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
ST1 Natural Gas Fired Combined Cycle 204 MW 2002 –
ST2 Natural Gas Fired Combined Cycle 204 MW 2002 –
CT1A Natural Gas Fired Combined Cycle 188 MW 2002 –
CT2A Natural Gas Fired Combined Cycle 182 MW 2002 –
CT2B Natural Gas Fired Combined Cycle 182 MW 2002 –
CT1B Natural Gas Fired Combined Cycle 168 MW 2002 –

Planned

GeneratorTechnologyCapacityExpected
CT10Natural Gas Fired Combustion Turbine49 MW2027
CT3Natural Gas Fired Combustion Turbine49 MW2027
CT4Natural Gas Fired Combustion Turbine49 MW2027
CT5Natural Gas Fired Combustion Turbine49 MW2027
CT6Natural Gas Fired Combustion Turbine49 MW2027
CT7Natural Gas Fired Combustion Turbine49 MW2027
CT8Natural Gas Fired Combustion Turbine49 MW2027
CT9Natural Gas Fired Combustion Turbine49 MW2027

Questions

Red Hawk, answered

How much power does Red Hawk produce?

Red Hawk has 1.1 GW of capacity from 6 generators. In 2025 it generated 4.8 TWh, 49% of the most it could have made running flat out all year (its capacity factor).

How many homes does Red Hawk power?

Its 2025 output of 4.8 TWh equals the yearly electricity use of about 392,000 average Arizona homes (1,030 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Red Hawk?

Red Hawk is in Maricopa County, Arizona, at about 33.335°, -112.841°. It is one of 82 power plants of 1 MW or more in the county. The average electricity customer in Maricopa County goes 1.5 hours a year without power, the 7th most of 11 counties in Arizona. The county's page has the full outage record.

Who operates Red Hawk?

It is operated by Arizona Public Service Co (EIA sector: Electric Utility), and it feeds Salt River Project.

When did Red Hawk open?

Its oldest generator still running came online in 2002. 8 more generators are planned.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Arizona home's 1,030 kWh a month in 2025. Methodology.