Data centers · Kentucky
Data centers in Kentucky
19 operating data center sites, 11 projects planned or under construction.
The map
Every mapped site
The pipeline
Projects on the way
From Civic Returns, Server Country, AI GridWatch, Megawattlas and the operators' own lists. Size is the developer's announced figure, often a full build-out over years. Projects with no published location are mapped at their city or county.
| Project | Developer | County | Status | Announced size | Year |
|---|---|---|---|---|---|
| PowerHouse Louisville | PowerHouse | Jefferson | Under construction | 402 MW | 2026 |
| TeraWulf Justified Data Campus (Hawesville) | TeraWulf (tenant: Anthropic) | Hancock | Under construction | 401 MW | 2027 |
| TeraWulf Justified Data | TeraWulf | Hancock | Under construction | – | – |
| Mason County Technology Campus | Fortune 100 Company (undisclosed) | Mason | Planned | 2.2 GW | – |
| TeraWulf Muskie Data Campus | TeraWulf | Greenup | Planned | 1.0 GW | 2030 |
| DartPoints Lexington Data Center | DartPoints Operating Company | Fayette | Planned | 70 MW | – |
| MD Squared Power Pikeville Data Center | MD Squared Power LLC | Pike | Planned | 30 MW | – |
| Cave City data center (Kentucky Industrial Alliance) | Kentucky Industrial Alliance LLC | Barren | Planned | – | – |
| Franklin-Simpson Data Storage and Service Center | TenKey LandCo I LLC | Simpson | Planned | – | – |
| Mercer County Data Center (Handy Road) | American Farm Investors | Mercer | Planned | – | – |
| Paducah DOE Data Center Campus | Brookfield / NextEra Energy (DOE site partnership) | McCracken | Planned | – | 2028 |
| Project Lincoln | Western Hospitality Partners | Oldham | Cancelled | – | – |
Local pushback
Bans and moratoriums
28 recorded as enacted, 0 proposed or under review, 1 expired, rejected or lifted (AI GridWatch). A time-limited moratorium with no documented end date keeps showing as enacted; check with the town or county.
| Where | Level | Status | Date | Runs |
|---|---|---|---|---|
| Woodford County · Woodford | County | Enacted | Sep 9, 2026 | No end date by design — a permanent ban or standing statute |
| Winchester · Clark | City | Enacted | Sep 2, 2026 | to Sep 2, 2027 |
| Louisville · Jefferson | Local | Enacted | Aug 13, 2026 | to Feb 13, 2027 |
| Jessamine County · Jessamine | Local | Enacted | Aug 4, 2026 | to Aug 4, 2027 |
| London · Laurel | Local | Enacted | Aug 3, 2026 | to Sep 30, 2028 |
| Clark County · Clark | County | Enacted | Aug 1, 2026 | A stated duration, but the end date isn't recorded here |
| Rowan County · Rowan | County | Enacted | Aug 1, 2026 | A stated duration, but the end date isn't recorded here |
| Lyon County · Lyon | Local | Enacted | Aug 1, 2026 | A stated duration, but the end date isn't recorded here |
| Nicholasville · Jessamine | Local | Enacted | Aug 1, 2026 | A stated duration, but the end date isn't recorded here |
| Mercer County · Mercer | Local | Enacted | Aug 1, 2026 | A stated duration, but the end date isn't recorded here |
| Logan County · Logan | Local | Enacted | Jul 30, 2026 | to Jul 30, 2027 |
| Georgetown · Scott | City | Enacted | Jul 14, 2026 | to Dec 31, 2026 |
| Boyd County · Boyd | County | Enacted | Jul 9, 2026 | to Jan 9, 2027 |
| Bell County · Bell | Local | Enacted | Jul 2, 2026 | to Jul 2, 2028 |
| Nelson County · Nelson | County | Enacted | Jul 1, 2026 | A stated duration, but the end date isn't recorded here |
| Shelby County · Shelby | County | Enacted | Jul 1, 2026 | to Dec 31, 2026 |
| Butler County · Butler | County | Enacted | Jun 26, 2026 | to Jun 26, 2027 |
| Versailles · Woodford | City | Enacted | Jun 17, 2026 | to Dec 31, 2026 |
| Boone County · Boone | County | Enacted | Jun 16, 2026 | to Jun 15, 2027 |
| Allen County · Allen | Local | Enacted | Jun 10, 2026 | to Jun 10, 2028 |
| Boyle County · Boyle | County | Enacted | Jun 9, 2026 | to Jun 9, 2027 |
| Lexington (Fayette County) · Fayette | Local | Expired | Jun 9, 2026 | to Oct 31, 2026 |
| Edmonson County · Edmonson | County | Enacted | Jun 8, 2026 | to Jun 8, 2027 |
| Daviess County · Daviess | Local | Enacted | May 28, 2026 | to May 28, 2027 |
| Cave City · Barren | Local | Enacted | May 20, 2026 | to May 20, 2027 |
| Scott County · Scott | County | Enacted | Mar 13, 2026 | A stated duration, but the end date isn't recorded here |
| Grant County · Grant | County | Enacted | Mar 2, 2026 | to Mar 2, 2028 |
| Bullitt County · Bullitt | County | Enacted | Jan 1, 2026 | to Jul 16, 2027 |
| Oldham County · Oldham | County | Enacted | Jan 1, 2025 | Runs until a condition is met, not to a date |
By county
Where the data centers cluster
| County | Mapped sites | Hours without power a year |
|---|---|---|
| Jefferson County | 6 | 5.8 h |
| Boone County | 3 | 2.3 h |
| McCracken County | 2 | 2.5 h |
| Marshall County | 2 | 5.3 h |
| Hopkins County | 1 | 9.8 h |
| Floyd County | 1 | 15 h |
| Fayette County | 1 | 7.2 h |
| Calloway County | 1 | 5.3 h |
| Shelby County | 1 | 2.7 h |
| Pike County | 1 | 16 h |
Every named site
The list
17 of 19 operating sites carry a name or operator; the rest are on the map above only. Area is the mapped outline (land for a campus, roof for a building).
| Site | Operator | County | Source | Acres |
|---|---|---|---|---|
| – | CyrusOne | Boone | Building | 3.2 |
| Core Scientific: Calvert 1, 2 & 3 | Core Scientific | Marshall | Civic Returns | 1.4 |
| Flexential Louisville - Downtown | Flexential | Jefferson | Building | 0.8 |
| Flexential Louisville - East | Flexential | Jefferson | Building | 0.8 |
| East Kentucky Network Datacenter | – | Floyd | Building | 0.4 |
| Cogent Louisville Data Center | Cogent Communications | Jefferson | Operator's own list | – |
| Cogent Louisville Edge Data Center | Cogent Communications | Jefferson | Operator's own list | – |
| Cogent Lexington Edge Data Center | Cogent Communications | Fayette | Operator's own list | – |
| Core Scientific Calvert 1, 2, & 3 | Core Scientific | Marshall | Operator's own list | – |
| Data Canopy Louisville, KY | Data Canopy | Jefferson | Operator's own list | – |
| MARA Murray Kentucky | MARA | Calloway | Operator's own list | – |
| Riot Platforms Kentucky - Commerce Drive | Riot Platforms | McCracken | Operator's own list | – |
| Lg&E Ku System Control & Data Center | – | Shelby | EPA record | – |
| Amazon Data Services Inc | Amazon Web Services | Boone | EPA record | – |
| Amazon Data Services Inc | Amazon Web Services | Boone | EPA record | – |
| Pikeville Medical Center Data Center | – | Pike | EPA record | – |
| Humana Data Center | – | Jefferson | EPA record | – |
How many data centers are in Kentucky?
19 operating or permitted sites on this map, from OpenStreetMap, EPA facility records and other open sources: the 33rd most of any state. 2 are mapped as whole campuses. The map covers most large sites, not every server room, so the true number is higher.
How many data centers are being built in Kentucky?
3 under construction and 8 planned or announced in the Civic Returns and Server Country databases; the 6 that publish a size add up to about 4.1 GW. 1 project has been cancelled.
Which Kentucky county has the most data centers?
Jefferson County, with 6 operating sites, then Boone County (3) and McCracken County (2).
Who operates data centers in Kentucky?
Among sites that name an operator: Cogent Communications (3), Core Scientific (2), Flexential (2), Amazon Web Services (2), CyrusOne (1).
What do Kentucky households pay for electricity?
13.1¢ per kWh on average in 2025 (US: 17.2¢), up 24% since 2018, from EIA-861. Prices move with fuel, storms and wires spending as well as new demand.
Sources: operating sites from OpenStreetMap © OpenStreetMap contributors (ODbL 1.0), read Nov 17, 2026; operators' own published facility lists; EPA ECHO facility records (public domain); Civic Returns, US Data Centers & Community Benefits Dataset (CC BY 4.0); Overture Maps places (CDLA-Permissive-2.0); Wikidata (CC0); EIA-860. Projects in development from Civic Returns, the Server Country project database, AI GridWatch and Megawattlas (all CC BY 4.0). Moratoriums from AI GridWatch (CC BY 4.0). AI campuses from Epoch AI, "AI data centers", CC BY 4.0. Electricity prices: EIA-861. Outage hours: ORNL EAGLE-I. How this is counted.