AI data center · Claude, Texas

Goodnight

Google's AI campus in Armstrong County. It is not drawing power yet and is planned to reach 1.29 GW by October 2027.

Power now–As of Apr 16, 2026
Planned peak1.29 GWOctober 2027
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Apr 16, 2026

What the satellite shows

Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. The substation expansion seems to be nearing completion.

Build-out

Power, month by month

0 MW500 MW1 GW1.5 GW20262027Today
Power drawn by Goodnight, from Epoch AI's dated observations and (hatched) its projections.
0 MW500 MW1 GW1.5 GW20262027Today
Power drawn by Goodnight, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Google (speculative)
Used by
Google DeepMind (speculative)
Built by
Crusoe, Hoffman
Energy companies
Serena
Chips
B300, Rubin
Address
10001 Lima Rd, Claude, TX 79019
County
Armstrong County (approximate)

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Claude, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Goodnight● Wind266 MW2.3 mi
Grandview Wind Farm, LLC● Wind211 MW9.5 mi
Colbeck's Corner, LLC● Wind200 MW14.2 mi
Route 66 Wind Plant● Wind150 MW7.9 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Apr 16, 2026Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. The substation expansion seems to be nearing completion.–
Dec 23, 2025Construction on Building 1 and 2 looks about halfway to completion. Foundations and utility trenches are visible for Building 3-4. Building 5-6 have an outline. The substation appears to be expanding.–
Oct 16, 2025Building 1 and 2 under construction.–
May 19, 2025Land clearing begins–

Plus 3 projected steps to October 2027, from Epoch AI's reading of the build plans.

How much power does Goodnight use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 1.29 GW by October 2027.

Who owns Goodnight?

Google (speculative); used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Goodnight?

In Armstrong County, the average customer is without power about 17 hours in a typical year in this site's outage record, with 51 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Goodnight?

4 plants within 15 miles total about 827 MW; the largest is Goodnight (266 MW, wind), 2.3 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.