Oracle's AI campus in Shackelford County. It is not drawing power yet and is planned to reach 1.96 GW by November 2028.
Latest look · Sep 4, 2026
What the satellite shows
Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Oracle
- Used by
- OpenAI
- Project
- Stargate
- Investors
- Oracle, OpenAI
- Chips
- Rubin
- Address
- 175 Private Road 1604, Abilene, TX 79601, Shackelford County
- County
- Shackelford County
Where
On the map of Texas
Placed at the centre of the county its address names; the exact site is not mapped here.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Mesquite Wind Power LLC | ● Wind | 200 MW | 11 mi |
| Hackberry Wind Farm | ● Wind | 166 MW | 6.7 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Sep 4, 2026 | Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway. | – |
| Apr 14, 2026 | Steel framing is underway for Buildings 1-3, and roofing is underway for Building 1. | – |
| Jan 18, 2026 | The layout of Buildings 1-5 is visible. Steel framing has just started on Building 1. | – |
| Aug 1, 2025 | Land clearing begins. | – |
Plus 10 projected steps to November 2028, from Epoch AI's reading of the build plans.
How much power does OpenAI Stargate Shackelford use?
It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 1.96 GW by November 2028.
Who owns OpenAI Stargate Shackelford?
Oracle; used by OpenAI. Investors: Oracle, OpenAI. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around OpenAI Stargate Shackelford?
In Shackelford County, the average customer is without power about 11 hours in a typical year in this site's outage record, with 63 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near OpenAI Stargate Shackelford?
2 plants within 15 miles total about 366 MW; the largest is Mesquite Wind Power LLC (200 MW, wind), 11 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Vantage data center page with power capacity, number of buildings, and first building timeline
- OpenAI Stargate expansion announcement mentioning Shackelford site
- Vantage LinkedIn post connecting the data center to OpenAI Stargate
- TDLR filing for first building (other buildings are also on TDLR)
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.