AI data center · Red Oak, Texas

Google Red Oak

Google's AI campus in Ellis County. It draws about 77 MW today and is planned to reach 185 MW by December 2026.

Power now77 MWAs of Feb 6, 2026
Planned peak185 MWDecember 2026
Compute108kH100-equivalent chips now
Capital cost$2.9BSo far, 2025 dollars

Latest look · Feb 6, 2026

What the satellite shows

Building 1 appears active - the surrounding land is finished including the site entrance and the parking lot. The dry coolers for Building 2 are nearly complete although the building is still clearly a construction zone. The Building 2 substation also appears complete.

Build-out

Power, month by month

0 MW50 MW100 MW150 MW200 MW202420252026Today
Power drawn by Google Red Oak, from Epoch AI's dated observations and (hatched) its projections.
0 MW50 MW100 MW150 MW200 MW202420252026Today
Power drawn by Google Red Oak, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Google
Chips
TPU v6e
Address
330 Austin Blvd, Red Oak, TX 75154
County
Ellis County

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Ameresco Dallas LLC● Biomass4 MW12.2 mi
WAL3285● Natural gas1 MW9.7 mi
WAL3432● Natural gas1 MW6.4 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Feb 6, 2026Building 1 appears active - the surrounding land is finished including the site entrance and the parking lot. The dry coolers for Building 2 are nearly complete although the building is still clearly a construction zone. The Building 2 substation also appears complete.93 MW
Aug 25, 2025Building 1 is operational, based on a Google Earth image showing a completed building shell and equipment, and the large construction car park being emptied. Building 2 shell looks mostly completed.93 MW
Apr 30, 2023First signs of development/land clearing–

Plus 1 projected step to December 2026, from Epoch AI's reading of the build plans.

How much power does Google Red Oak use?

About 77 MW as of Feb 6, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 185 MW in its build plans by December 2026. Running all year, 77 MW would use about 0.7 TWh.

Who owns Google Red Oak?

Google. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Red Oak?

In Ellis County, the average customer is without power about 7.7 hours in a typical year in this site's outage record, with 10 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google Red Oak?

3 plants within 15 miles total about 7 MW; the largest is Ameresco Dallas LLC (4 MW, biomass), 12.2 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.