AI data center · Colorado City, Texas

Anthropic Barber Lake

Cipher Mining's AI campus in Mitchell County. It is not drawing power yet and is planned to reach 300 MW by April 2027.

Power now–As of Jul 30, 2026
Planned peak300 MWApril 2027
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Jul 30, 2026

What the satellite shows

Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW20262027Today
Power drawn by Anthropic Barber Lake, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW400 MW20262027Today
Power drawn by Anthropic Barber Lake, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Cipher Mining
Used by
Anthropic
Chips
TPU v7
County
Mitchell County (approximate)

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Colorado City, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Morgan Creek● Oil536 MW5.5 mi
Roscoe Wind Farm LLC● Wind209 MW12.2 mi
Loraine Windpark Project LLC● Wind150 MW7.1 mi
Champion Wind Farm LLC● Wind127 MW12.3 mi
Lone Wolfe Phase One● Solar1 MW7.8 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jul 30, 2026Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.–
Nov 29, 2025Foundations of Building 1 are visible.–
Sep 18, 2025Site grading and civil works begin.–

Plus 2 projected steps to April 2027, from Epoch AI's reading of the build plans.

How much power does Anthropic Barber Lake use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 300 MW by April 2027.

Who owns Anthropic Barber Lake?

Cipher Mining; used by Anthropic. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Anthropic Barber Lake?

In Mitchell County, the average customer is without power about 13 hours in a typical year in this site's outage record, with 58 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Anthropic Barber Lake?

5 plants within 15 miles total about 1.02 GW; the largest is Morgan Creek (536 MW, oil), 5.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.