AI data center · Abilene, Texas

OpenAI Stargate Abilene

Oracle's AI campus in Taylor County. It draws about 824 MW today and is planned to reach 1.15 GW by November 2026.

Power now824 MWAs of Nov 1, 2026
Planned peak1.15 GWNovember 2026
Compute1.02MH100-equivalent chips now
Capital cost$31BSo far, 2025 dollars

Latest look · Nov 1, 2026

What the satellite shows

Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This naively suggests Building 8 will be operational by early November, 7 months after March 24. Oracle gave no date for the last two buildings on its September 10 call.

Build-out

Power, month by month

0 MW500 MW1 GW1.5 GW20252026Today
Power drawn by OpenAI Stargate Abilene, from Epoch AI's dated observations.
0 MW500 MW1 GW1.5 GW20252026Today
Power drawn by OpenAI Stargate Abilene, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Oracle
Used by
OpenAI
Project
Stargate
Investors
Softbank, OpenAI, Oracle
Built by
Mortenson
Energy companies
American Electric Power
Chips
B200, B300
Address
5502 Spinks Rd, Abilene, TX 79601
County
Taylor County

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Post Oak Wind LLC● Wind200 MW8.5 mi
DGS Five Points● Storage10 MW2.1 mi
Plaza Street● Storage10 MW2.6 mi
WAL536● Natural gas1 MW6.1 mi
HEB00070● Natural gas1 MW4.9 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Nov 1, 2026Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This naively suggests Building 8 will be operational by early November, 7 months after March 24. Oracle gave no date for the last two buildings on its September 10 call.1.15 GW
Sep 10, 2026Buildings 5-6 are operational. On Oracle's Q1 FY27 earnings call (September 10, 2026), Clay Magouyrk said "6 of the 8 campus buildings, representing 618 megawatts and 75% of total capacity have now been delivered to the customer" (transcript). 618 MW = 6 x 103 MW, matching the per-building IT power figure Crusoe reported earlier. Since Oracle is the chip owner rather than the facility operator, we assume "delivered" means the chips are installed and ready to use.865 MW
Jul 28, 2026Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete.577 MW
May 23, 2026Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 and 4 looked complete from the outside on March 24th, we give it another month after Oracle's post for them to be operational. This would also give the buildings a similar 1 year 4 months timeline that Buildings 1 took from land clearing to being operational.577 MW
Mar 24, 2026Building 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according to a regulatory filing. Building 5 still has light construction activity, while Building 6 still lacks chillers. The on-site power plant to the right of Building 2 looks complete.288 MW
Jan 15, 2026The 1 GW substation looks close to completion. Building 3 appears to have all power and cooling equipment installed, but there are still signs of construction work. This seems on track for operation in 3 months. Building 4 has about 80% of chillers installed. Other buildings have few or no chillers installed.288 MW
Dec 24, 2025Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a TDLR filing, but this date is also consistent with satellite imagery. By January 15, Building 2 looked as finished as Building 1, whereas on September 26 it did not look finished.288 MW
Sep 26, 2025Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe announcement. While the first phase consists of Building 1 and 2, the language doesn't outright confirm that both buildings are fully operational. The announcement also stated that "Oracle began delivering the first NVIDIA GB200 racks in June", and we think 3 months is enough time to ram to 50,000 GB200s in Building 1. The satellite image also suggests that Building 1 is complete (shell and equipment done, many cars neatly parked) while Building 2 is ongoing (trucks and construction equipment still present). The 200 MW substation built in 2022 and expanded in 2024 is enough to power both buildings. To the right of Building 2, five gas turbines are in place with five more turbines still under construction. Chillers are partly installed for Building 3. Roof is complete for Building 4. The larger 1 GW substation is not complete yet.144 MW
Jun 28, 2025Building 1 looks close to finishing construction, with chillers in place. OpenAI stated that "Oracle began delivering the first NVIDIA GB200 racks in June." The "tenant improvement" work is not due until September, however.–
May 31, 2024Land clearing begins for northern two buildings (Building 1-2)–

How much power does OpenAI Stargate Abilene use?

About 824 MW as of Nov 1, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 1.15 GW in its build plans by November 2026. Running all year, 824 MW would use about 7.2 TWh.

Who owns OpenAI Stargate Abilene?

Oracle; used by OpenAI. Investors: Softbank, OpenAI, Oracle. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around OpenAI Stargate Abilene?

In Taylor County, the average customer is without power about 8.4 hours in a typical year in this site's outage record, with 13 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near OpenAI Stargate Abilene?

5 plants within 15 miles total about 222 MW; the largest is Post Oak Wind LLC (200 MW, wind), 8.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.