AI data center · Temple, Texas

Meta Temple

Meta's AI campus in Bell County. It draws about 178 MW today and is planned to reach 231 MW by September 2026.

Power now178 MWAs of Sep 30, 2026
Planned peak231 MWSeptember 2026
Compute202kH100-equivalent chips now
Capital cost$6.7BSo far, 2025 dollars

Latest look · Sep 30, 2026

What the satellite shows

Building 3 is operational. Based on the stated completion date in this regulatory filing

Build-out

Power, month by month

0 MW50 MW100 MW150 MW200 MW250 MW2023202420252026
Power drawn by Meta Temple, from Epoch AI's dated observations.
0 MW50 MW100 MW150 MW200 MW250 MW2023202420252026
Power drawn by Meta Temple, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Meta
Used by
Meta
Built by
JE Dunn
Chips
B300
Address
2310 Eberhardt Rd, Temple, TX 76504
County
Bell County

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Temple Power Station● Natural gas1.61 GW5.5 mi
Five Wells Solar Center - Hybrid● Solar618 MW10.6 mi
Blevins Solar & Storage● Solar450 MW11.9 mi
Big Elm Solar● Solar200 MW8.5 mi
Chillingham Storage● Storage150 MW10.1 mi
Eddy II● Solar10 MW12.8 mi
HEBTEMDistCenter● Natural gas6 MW1.8 mi
HEBTEMDistCenter2A● Natural gas6 MW1.8 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Sep 30, 2026Building 3 is operational. Based on the stated completion date in this regulatory filing231 MW
Feb 24, 2026Building 3 is under construction. An outline is visible for the building which has similar dimensions to those deployed at the Meta Prometheus site.198 MW
Dec 9, 2025Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best estimate, but note that the planned completion date in this regulatory filing is 2026-03-01.198 MW
Nov 15, 2025Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Space is cleared for Building 3.–
Apr 1, 2023The traditional Meta data center has been demolished mid-construction, in favor of Meta's new AI-optimized design.–
Feb 5, 2023A traditional H-shaped Meta data center is partially built.–
Apr 1, 2022Land clearing begins.–

How much power does Meta Temple use?

About 178 MW as of Sep 30, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 231 MW in its build plans by September 2026. Running all year, 178 MW would use about 1.6 TWh.

Who owns Meta Temple?

Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Meta Temple?

In Bell County, the average customer is without power about 8.1 hours in a typical year in this site's outage record, with 5 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Meta Temple?

8 plants within 15 miles total about 3.05 GW; the largest is Temple Power Station (1.61 GW, natural gas), 5.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.