AI data center · Afton, Texas
Coreweave Helios
CoreWeave's AI campus in Dickens County. It draws about 132 MW today and is planned to reach 800 MW by January 2029.
Latest look · Aug 30, 2026
What the satellite shows
Building 1 operational at full capacity. This is based on "Phase I", which is expected to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- CoreWeave
- Used by
- OpenAI (speculative)
- Chips
- B200
- Address
- 984 County Road 112, Afton, TX 79220
- County
- Dickens County
Where
On the map of Texas
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Wake Wind Energy Center | ● Wind | 257 MW | 13.7 mi |
| Roaring Springs, LLC | ● Solar | 250 MW | 6.8 mi |
| Dickens | ● Storage | 200 MW | 0.9 mi |
| McAdoo Wind Energy LLC | ● Wind | 150 MW | 6.1 mi |
| Burksol Energy Storage | ● Storage | 100 MW | 0.6 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Aug 30, 2026 | Building 1 operational at full capacity. This is based on "Phase I", which is expected to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building. | 200 MW |
| Jun 17, 2026 | Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work. CoreWeave likely still needs time to install chips and use all their designated chip capacity. The pad to the northeast has foundations being laid out for Building 2. | – |
| Apr 4, 2026 | Building 1 appears substantially complete. The main white-roofed data hall is visible with exterior mechanical/electrical equipment rows installed on both sides, and adjacent generator/equipment pads plus laydown yards are active. A large graded pad north of Building 1 suggests preparation for the next phase/building. No clear satellite evidence that the AI/HPC facility is operational yet. | – |
| Aug 27, 2025 | Backup generator pads and steel framing for chillers are visible, similar to the 3D renderings. | – |
| May 31, 2025 | Land clearing: The former crypto mining Helios site begins converting the first building and expanding, with land cleared for additional buildings. | – |
Plus 2 projected steps to January 2029, from Epoch AI's reading of the build plans.
How much power does Coreweave Helios use?
About 132 MW as of Aug 30, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 800 MW in its build plans by January 2029. Running all year, 132 MW would use about 1.2 TWh.
Who owns Coreweave Helios?
CoreWeave; used by OpenAI (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Coreweave Helios?
In Dickens County, the average customer is without power about 7.9 hours in a typical year in this site's outage record, with 45 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Coreweave Helios?
5 plants within 15 miles total about 957 MW; the largest is Wake Wind Energy Center (257 MW, wind), 13.7 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Galaxy Q3 financial results with power capacity timeline
- Permit review with details on backup generators and power capacity
- 3D renderings of Helios Building 1 on Galaxy's website, showing generators and chillers
- TDLR record with Building 1 construction costs and end date
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.