AI data center · Afton, Texas

Coreweave Helios

CoreWeave's AI campus in Dickens County. It draws about 132 MW today and is planned to reach 800 MW by January 2029.

Power now132 MWAs of Aug 30, 2026
Planned peak800 MWJanuary 2029
Compute160kH100-equivalent chips now
Capital cost$5.0BSo far, 2025 dollars

Latest look · Aug 30, 2026

What the satellite shows

Building 1 operational at full capacity. This is based on "Phase I", which is expected to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building.

Build-out

Power, month by month

0 MW200 MW400 MW600 MW800 MW1 GW2026202720282029Today
Power drawn by Coreweave Helios, from Epoch AI's dated observations and (hatched) its projections.
0 MW200 MW400 MW600 MW800 MW1 GW2026202720282029Today
Power drawn by Coreweave Helios, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
CoreWeave
Used by
OpenAI (speculative)
Chips
B200
Address
984 County Road 112, Afton, TX 79220
County
Dickens County

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Wake Wind Energy Center● Wind257 MW13.7 mi
Roaring Springs, LLC● Solar250 MW6.8 mi
Dickens● Storage200 MW0.9 mi
McAdoo Wind Energy LLC● Wind150 MW6.1 mi
Burksol Energy Storage● Storage100 MW0.6 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Aug 30, 2026Building 1 operational at full capacity. This is based on "Phase I", which is expected to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building.200 MW
Jun 17, 2026Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work. CoreWeave likely still needs time to install chips and use all their designated chip capacity. The pad to the northeast has foundations being laid out for Building 2.–
Apr 4, 2026Building 1 appears substantially complete. The main white-roofed data hall is visible with exterior mechanical/electrical equipment rows installed on both sides, and adjacent generator/equipment pads plus laydown yards are active. A large graded pad north of Building 1 suggests preparation for the next phase/building. No clear satellite evidence that the AI/HPC facility is operational yet.–
Aug 27, 2025Backup generator pads and steel framing for chillers are visible, similar to the 3D renderings.–
May 31, 2025Land clearing: The former crypto mining Helios site begins converting the first building and expanding, with land cleared for additional buildings.–

Plus 2 projected steps to January 2029, from Epoch AI's reading of the build plans.

How much power does Coreweave Helios use?

About 132 MW as of Aug 30, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 800 MW in its build plans by January 2029. Running all year, 132 MW would use about 1.2 TWh.

Who owns Coreweave Helios?

CoreWeave; used by OpenAI (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Coreweave Helios?

In Dickens County, the average customer is without power about 7.9 hours in a typical year in this site's outage record, with 45 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Coreweave Helios?

5 plants within 15 miles total about 957 MW; the largest is Wake Wind Energy Center (257 MW, wind), 13.7 miles away. Nearness does not mean it supplies the campus.