AI data center · Burlington, Texas

OpenAI Stargate Milam

Softbank's AI campus in Milam County. It is not drawing power yet and is planned to reach 1.20 GW by December 2028.

Power now–As of Mar 23, 2026
Planned peak1.20 GWDecember 2028
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Mar 23, 2026

What the satellite shows

Steel framing and roofing is underway for Building 1.

Build-out

Power, month by month

0 MW500 MW1 GW1.5 GW202620272028Today
Power drawn by OpenAI Stargate Milam, from Epoch AI's dated observations and (hatched) its projections.
0 MW500 MW1 GW1.5 GW202620272028Today
Power drawn by OpenAI Stargate Milam, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Softbank
Used by
OpenAI
Project
Stargate
County
Milam County (approximate)

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Burlington, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Orion III Solar Project● Solar250 MW8.5 mi
Orion II Solar Project● Solar250 MW3.8 mi
Stillhouse Solar● Solar210 MW10.6 mi
Yaupon Solar Project (Hybrid)● Solar200 MW8.7 mi
Orion I Solar Project● Solar200 MW0.8 mi
BT Jungmann● Solar40 MW8 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Mar 23, 2026Steel framing and roofing is underway for Building 1.–
Jan 4, 2026Small sections of building foundation construction begins, and land clearing appears to be mostly finished–
Sep 27, 2025Land clearing begins for the site–

Plus 1 projected step to December 2028, from Epoch AI's reading of the build plans.

How much power does OpenAI Stargate Milam use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 1.20 GW by December 2028.

Who owns OpenAI Stargate Milam?

Softbank; used by OpenAI. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around OpenAI Stargate Milam?

In Milam County, the average customer is without power about 15 hours in a typical year in this site's outage record, with 30 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near OpenAI Stargate Milam?

6 plants within 15 miles total about 1.15 GW; the largest is Orion III Solar Project (250 MW, solar), 8.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.