AI data center · San Antonio, Texas
Microsoft SAT14
Microsoft's AI campus in Bexar County. It draws about 47 MW today and is planned to reach 66 MW by March 2026.
Latest look · Mar 31, 2026
What the satellite shows
Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Microsoft
- Chips
- H100, B300
- Address
- 3545 Wiseman Boulevard, San Antonio, TX 78251
- County
- Bexar County
Where
On the map of Texas
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Leon Creek | ● Natural gas | 230 MW | 10.5 mi |
| Ferdinand Energy Center | ● Storage | 200 MW | 10.7 mi |
| Commerce ESS | ● Storage | 10 MW | 4.7 mi |
| Ranchtown | ● Storage | 10 MW | 10.5 mi |
| Commerce Solar | ● Solar | 5 MW | 4.7 mi |
| Nelson Gardens Landfill Gas to Energy | ● Biomass | 4 MW | 10 mi |
| HEB_CPS00085 | ● Natural gas | 2 MW | 3 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Mar 31, 2026 | Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31. | 66 MW |
| Feb 28, 2026 | No more visible construction around either building, just a little equipment. Roads fully built around buildings as well. | 26 MW |
| Aug 3, 2025 | Building 2 chiller installation is a little more than halfway complete, and chiller installation for the last data hall of Building 1 is also around halfway complete. | 26 MW |
| Jul 1, 2024 | Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the on-site substation was previously incomplete, so we believe it was only operational at this point. | 26 MW |
| Feb 18, 2022 | Land clearing for the site is almost complete. Informed using imagery on Google Earth | – |
How much power does Microsoft SAT14 use?
About 47 MW as of Mar 31, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 66 MW in its build plans by March 2026. Running all year, 47 MW would use about 0.4 TWh.
Who owns Microsoft SAT14?
Microsoft. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Microsoft SAT14?
In Bexar County, the average customer is without power about 3.3 hours in a typical year in this site's outage record, with 1 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Microsoft SAT14?
7 plants within 15 miles total about 460 MW; the largest is Leon Creek (230 MW, natural gas), 10.5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.