AI data center · San Antonio, Texas

Microsoft SAT14

Microsoft's AI campus in Bexar County. It draws about 47 MW today and is planned to reach 66 MW by March 2026.

Power now47 MWAs of Mar 31, 2026
Planned peak66 MWMarch 2026
Compute45kH100-equivalent chips now
Capital cost$1.8BSo far, 2025 dollars

Latest look · Mar 31, 2026

What the satellite shows

Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31.

Build-out

Power, month by month

0 MW20 MW40 MW60 MW80 MW2023202420252026
Power drawn by Microsoft SAT14, from Epoch AI's dated observations.
0 MW20 MW40 MW60 MW80 MW2023202420252026
Power drawn by Microsoft SAT14, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Microsoft
Chips
H100, B300
Address
3545 Wiseman Boulevard, San Antonio, TX 78251
County
Bexar County

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Leon Creek● Natural gas230 MW10.5 mi
Ferdinand Energy Center● Storage200 MW10.7 mi
Commerce ESS● Storage10 MW4.7 mi
Ranchtown● Storage10 MW10.5 mi
Commerce Solar● Solar5 MW4.7 mi
Nelson Gardens Landfill Gas to Energy● Biomass4 MW10 mi
HEB_CPS00085● Natural gas2 MW3 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Mar 31, 2026Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31.66 MW
Feb 28, 2026No more visible construction around either building, just a little equipment. Roads fully built around buildings as well.26 MW
Aug 3, 2025Building 2 chiller installation is a little more than halfway complete, and chiller installation for the last data hall of Building 1 is also around halfway complete.26 MW
Jul 1, 2024Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the on-site substation was previously incomplete, so we believe it was only operational at this point.26 MW
Feb 18, 2022Land clearing for the site is almost complete. Informed using imagery on Google Earth–

How much power does Microsoft SAT14 use?

About 47 MW as of Mar 31, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 66 MW in its build plans by March 2026. Running all year, 47 MW would use about 0.4 TWh.

Who owns Microsoft SAT14?

Microsoft. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Microsoft SAT14?

In Bexar County, the average customer is without power about 3.3 hours in a typical year in this site's outage record, with 1 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Microsoft SAT14?

7 plants within 15 miles total about 460 MW; the largest is Leon Creek (230 MW, natural gas), 10.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.