AI data center · Abilene, Texas
Crusoe Abilene Expansion
Microsoft's AI campus in Taylor County. It is not drawing power yet and is planned to reach 941 MW by November 2027.
Latest look · Jan 15, 2026
What the satellite shows
Land clearing continues.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Microsoft
- Used by
- Microsoft (likely)
- Investors
- NVIDIA
- Chips
- Rubin
- Address
- 5502 Spinks Rd, Abilene, TX 79601
- County
- Taylor County
Where
On the map of Texas
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Post Oak Wind LLC | ● Wind | 200 MW | 8.5 mi |
| DGS Five Points | ● Storage | 10 MW | 2.1 mi |
| Plaza Street | ● Storage | 10 MW | 2.6 mi |
| WAL536 | ● Natural gas | 1 MW | 6.1 mi |
| HEB00070 | ● Natural gas | 1 MW | 4.9 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jan 15, 2026 | Land clearing continues. | – |
| Nov 2, 2025 | Land clearing begins for Buildings 1-2. | – |
Plus 2 projected steps to November 2027, from Epoch AI's reading of the build plans.
How much power does Crusoe Abilene Expansion use?
It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 941 MW by November 2027.
Who owns Crusoe Abilene Expansion?
Microsoft; used by Microsoft (likely). Investors: NVIDIA. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Crusoe Abilene Expansion?
In Taylor County, the average customer is without power about 8.4 hours in a typical year in this site's outage record, with 13 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Crusoe Abilene Expansion?
5 plants within 15 miles total about 222 MW; the largest is Post Oak Wind LLC (200 MW, wind), 8.5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Bloomberg reporting that Oracle and OpenAI pulled out of expanding to these buildings, NVIDIA and Meta might replace them
- Air Permit Application for the buildings, featuring blueprints on p.391
- Aterio
- Partnership Announcement with Microsoft
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.