AI data center · Denton, Texas
CoreWeave Denton TX
CoreWeave's AI campus in Denton County. It draws about 262 MW today and is planned to reach 395 MW by May 2027.
Latest look · Sep 1, 2026
What the satellite shows
Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- CoreWeave
- Used by
- OpenAI (likely)
- Chips
- B200
- Address
- 8171 Jim Christal Rd, Denton, TX 76207
- County
- Denton County
Where
On the map of Texas
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Noble Solar | ● Solar | 400 MW | 4.7 mi |
| Porter Solar, LLC (TX) | ● Solar | 245 MW | 12.9 mi |
| Denton Energy Center | ● Natural gas | 226 MW | 2 mi |
| Spencer | ● Natural gas | 127 MW | 4.2 mi |
| Connolly BESS | ● Storage | 125 MW | 14.1 mi |
| TX10 Hummingbird Storage | ● Storage | 100 MW | 10.9 mi |
| BKV-BPP Ponder Solar | ● Solar | 3 MW | 6.4 mi |
| CoServ Community Solar Station | ● Solar | 2 MW | 11.8 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Sep 1, 2026 | Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026. | 367 MW |
| Jul 3, 2026 | Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the Q2 2026 Earnings call stating the campus was operational by midyear 2026. | 367 MW |
| Mar 2, 2026 | Buildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an earnings call from this date. | 183 MW |
| Feb 23, 2026 | Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. This is according to satellite imagery. | 183 MW |
| Dec 31, 2025 | Half the campus energized. 67 billable MW are now dedicated to CoreWeave's GPUs across three buildings. | 94 MW |
| May 31, 2025 | First 8 MW billable tranche dedicated to AI starts running at the site, with another 40 scheduled by the end of the quarter. | 11 MW |
| Nov 1, 2024 | Construction start - The Texas Department of Licensing and Regulation reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy Center. | – |
Plus 1 projected step to May 2027, from Epoch AI's reading of the build plans.
How much power does CoreWeave Denton TX use?
About 262 MW as of Sep 1, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 395 MW in its build plans by May 2027. Running all year, 262 MW would use about 2.3 TWh.
Who owns CoreWeave Denton TX?
CoreWeave; used by OpenAI (likely). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around CoreWeave Denton TX?
In Denton County, the average customer is without power about 4.5 hours in a typical year in this site's outage record, with 4 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near CoreWeave Denton TX?
8 plants within 15 miles total about 1.23 GW; the largest is Noble Solar (400 MW, solar), 4.7 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Core Scientific - CoreWeave Announce 1.2B expansion in Denton, TX
- Core Scientific - Denton Datacenter Official Site
- TMF - Core Scientific Q4 2025 Earnings Transcript
- WSJ - plans to rent to OpenAI
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.