AI data center · Denton, Texas

CoreWeave Denton TX

CoreWeave's AI campus in Denton County. It draws about 262 MW today and is planned to reach 395 MW by May 2027.

Power now262 MWAs of Sep 1, 2026
Planned peak395 MWMay 2027
Compute253kH100-equivalent chips now
Capital cost$9.9BSo far, 2025 dollars

Latest look · Sep 1, 2026

What the satellite shows

Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW500 MW202520262027Today
Power drawn by CoreWeave Denton TX, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW400 MW500 MW202520262027Today
Power drawn by CoreWeave Denton TX, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
CoreWeave
Used by
OpenAI (likely)
Chips
B200
Address
8171 Jim Christal Rd, Denton, TX 76207
County
Denton County

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Noble Solar● Solar400 MW4.7 mi
Porter Solar, LLC (TX)● Solar245 MW12.9 mi
Denton Energy Center● Natural gas226 MW2 mi
Spencer● Natural gas127 MW4.2 mi
Connolly BESS● Storage125 MW14.1 mi
TX10 Hummingbird Storage● Storage100 MW10.9 mi
BKV-BPP Ponder Solar● Solar3 MW6.4 mi
CoServ Community Solar Station● Solar2 MW11.8 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Sep 1, 2026Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.367 MW
Jul 3, 2026Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the Q2 2026 Earnings call stating the campus was operational by midyear 2026.367 MW
Mar 2, 2026Buildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an earnings call from this date.183 MW
Feb 23, 2026Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. This is according to satellite imagery.183 MW
Dec 31, 2025Half the campus energized. 67 billable MW are now dedicated to CoreWeave's GPUs across three buildings.94 MW
May 31, 2025First 8 MW billable tranche dedicated to AI starts running at the site, with another 40 scheduled by the end of the quarter.11 MW
Nov 1, 2024Construction start - The Texas Department of Licensing and Regulation reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy Center.–

Plus 1 projected step to May 2027, from Epoch AI's reading of the build plans.

How much power does CoreWeave Denton TX use?

About 262 MW as of Sep 1, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 395 MW in its build plans by May 2027. Running all year, 262 MW would use about 2.3 TWh.

Who owns CoreWeave Denton TX?

CoreWeave; used by OpenAI (likely). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around CoreWeave Denton TX?

In Denton County, the average customer is without power about 4.5 hours in a typical year in this site's outage record, with 4 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near CoreWeave Denton TX?

8 plants within 15 miles total about 1.23 GW; the largest is Noble Solar (400 MW, solar), 4.7 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.