Solar power plant · Denton, TX
Noble Solar
Noble Solar is a 400 MW solar power plant in Denton County, Texas, operated by Geronimo Power. Its oldest generator still running came online in 2022. In 2025 it generated 528 GWh, about what 40,000 average Texas homes use in a year.
Noble Solar in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 20th largest, about 1.1% of the state's 37 GW of solar capacity.
Denton County has 11 power plants of 1 MW or more with 1.1 GW in all; Noble Solar is 36% of that and the largest of 4 solar plants there.
Its capacity factor of 15% in 2025 is lower than the 20% typical for solar plants across the US.
The average electricity customer in Denton County goes 4.5 hours a year without power, the 203rd most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Noble Solar (outlined) and other plants in Denton County, shaded. 33.262, -97.238.
Plant facts
- Operator
- Geronimo Power
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Denton County, TX
- EIA plant ID
- 65271
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| NBSLR | Solar Photovoltaic | 275 MW | 2022 | – |
| NBSTG | Batteries | 125 MW · 125 MWh | 2022 | – |
Nearby
Other plants in Denton County
Questions
Noble Solar, answered
How much power does Noble Solar produce?
Noble Solar has 400 MW of capacity from 2 generators. In 2025 it generated 528 GWh, 15% of the most it could have made running flat out all year (its capacity factor).
How many homes does Noble Solar power?
Its 2025 output of 528 GWh equals the yearly electricity use of about 40,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Noble Solar?
Noble Solar is in Denton County, Texas, at about 33.262°, -97.238°. It is one of 11 power plants of 1 MW or more in the county. The average electricity customer in Denton County goes 4.5 hours a year without power, the 203rd most of 240 counties in Texas. The county's page has the full outage record.
Who operates Noble Solar?
It is operated by Geronimo Power (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Noble Solar open?
Its oldest generator still running came online in 2022.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2022–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.