AI data center · San Antonio, Texas

Vantage TX1

AI campus in Bexar County. It draws about 32 MW today and is planned to reach 179 MW by August 2027.

Power now32 MWAs of Feb 15, 2026
Planned peak179 MWAugust 2027
Compute39kH100-equivalent chips now
Capital cost$1.2BSo far, 2025 dollars

Latest look · Feb 15, 2026

What the satellite shows

Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the completion date reported on TDLR, based on the appearance, we believe it is operational. Reported IT power of 32 MW. Source

Build-out

Power, month by month

0 MW50 MW100 MW150 MW200 MW2024202520262027Today
Power drawn by Vantage TX1, from Epoch AI's dated observations and (hatched) its projections.
0 MW50 MW100 MW150 MW200 MW2024202520262027Today
Power drawn by Vantage TX1, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Chips
B200
Address
14720 Omicron Dr, San Antonio, TX 78245
County
Bexar County

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Leon Creek● Natural gas230 MW13.5 mi
Ferdinand Energy Center● Storage200 MW13.6 mi
Commerce ESS● Storage10 MW10.4 mi
Ranchtown● Storage10 MW14.3 mi
Commerce Solar● Solar5 MW10.4 mi
Nelson Gardens Landfill Gas to Energy● Biomass4 MW9.8 mi
HEB_CPS00085● Natural gas2 MW5.3 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Feb 15, 2026Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the completion date reported on TDLR, based on the appearance, we believe it is operational. Reported IT power of 32 MW. Source45 MW
Dec 15, 2023Land clearing begins for both Building 1 & Building 2–

Plus 1 projected step to August 2027, from Epoch AI's reading of the build plans.

How much power does Vantage TX1 use?

About 32 MW as of Feb 15, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 179 MW in its build plans by August 2027. Running all year, 32 MW would use about 0.3 TWh.

How reliable is the power around Vantage TX1?

In Bexar County, the average customer is without power about 3.3 hours in a typical year in this site's outage record, with 1 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Vantage TX1?

7 plants within 15 miles total about 460 MW; the largest is Leon Creek (230 MW, natural gas), 13.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.