Storage power plant · Bexar, TX
Ferdinand Energy Center
Ferdinand Energy Center is a 200 MW storage power plant in Bexar County, Texas, operated by Ferdinand Grid, LLC. Its oldest generator still running came online in 2026.
Ferdinand Energy Center in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 29th largest, about 1.2% of the state's 16 GW of storage capacity.
Bexar County has 26 power plants of 1 MW or more with 5.0 GW in all; Ferdinand Energy Center is 4% of that and the largest of 7 storage plants there.
The average electricity customer in Bexar County goes 3.3 hours a year without power, the 219th most of 240 counties in Texas. The county's page has the full outage record.
Where it is
Ferdinand Energy Center (outlined) and other plants in Bexar County, shaded. 29.348, -98.577.
Plant facts
- Operator
- Ferdinand Grid, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Bexar County, TX
- EIA plant ID
- 68915
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Batteries | 200 MW · 800 MWh | 2026 | – |
Questions
Ferdinand Energy Center, answered
How much can Ferdinand Energy Center store and deliver?
Ferdinand Energy Center can deliver up to 200 MW and hold 800 MWh of energy, from one battery or storage system.
Where is Ferdinand Energy Center?
Ferdinand Energy Center is in Bexar County, Texas, at about 29.348°, -98.577°. It is one of 26 power plants of 1 MW or more in the county. The average electricity customer in Bexar County goes 3.3 hours a year without power, the 219th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Ferdinand Energy Center?
It is operated by Ferdinand Grid, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Ferdinand Energy Center open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.