AI data center · San Antonio, Texas

Microsoft SAT40

Microsoft's AI campus in Bexar County. It draws about 75 MW today and is planned to reach 106 MW by December 2025.

Power now75 MWAs of Feb 4, 2026
Planned peak106 MWDecember 2025
Compute65kH100-equivalent chips now
Capital cost$2.8BSo far, 2025 dollars

Latest look · Feb 4, 2026

What the satellite shows

Site has already been completed, with no more visible construction on any building.

Build-out

Power, month by month

0 MW20 MW40 MW60 MW80 MW100 MW120 MW20192020202120222023202420252026
Power drawn by Microsoft SAT40, from Epoch AI's dated observations.
0 MW20 MW40 MW60 MW80 MW100 MW120 MW2020202220242026
Power drawn by Microsoft SAT40, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Microsoft
Chips
H100, B300
Address
15000 Lambda Drive, San Antonio, TX 78245
County
Bexar County (approximate)

Where

On the map of Texas

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of San Antonio, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Leon Creek● Natural gas230 MW8.2 mi
Ferdinand Energy Center● Storage200 MW8.5 mi
Bexar ESS● Storage100 MW13.9 mi
OCI Alamo Solar I Hybrid● Solar41 MW14.1 mi
Blue Wing Solar Energy Generation● Solar14 MW13.3 mi
Commerce ESS● Storage10 MW5.9 mi
Bexar Corrilla BESS● Storage10 MW13.8 mi
HEB_CPSSADC● Natural gas6 MW10.3 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Feb 4, 2026Site has already been completed, with no more visible construction on any building.106 MW
Dec 1, 2025Building 2 operational. No more construction on building, and surrounding roads are also complete.106 MW
May 24, 2024Building 1 operational. Estimated 3 months out from February, when there was still construction equipment.66 MW
Dec 28, 2018Land clearing begins for the site, specifically digging up a parking lot and making outlines for the buildings. Evident on Google Earth.–

How much power does Microsoft SAT40 use?

About 75 MW as of Feb 4, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 106 MW in its build plans by December 2025. Running all year, 75 MW would use about 0.7 TWh.

Who owns Microsoft SAT40?

Microsoft. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Microsoft SAT40?

In Bexar County, the average customer is without power about 3.3 hours in a typical year in this site's outage record, with 1 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Microsoft SAT40?

8 plants within 15 miles total about 631 MW; the largest is Leon Creek (230 MW, natural gas), 8.2 miles away. Nearness does not mean it supplies the campus.