Solar power plant · Bell, TX
Five Wells Solar Center - Hybrid
Five Wells Solar Center - Hybrid is a 618 MW solar power plant in Bell County, Texas, operated by Five Wells Solar Center, LLC. Its oldest generator still running came online in 2023. In 2025 it generated 723 GWh, about what 54,000 average Texas homes use in a year.
Five Wells Solar Center - Hybrid in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 2nd largest, about 1.7% of the state's 37 GW of solar capacity.
Bell County has 12 power plants of 1 MW or more with 2.8 GW in all; Five Wells Solar Center - Hybrid is 22% of that and the largest of 4 solar plants there.
Its capacity factor of 13% in 2025 is lower than the 20% typical for solar plants across the US.
The average electricity customer in Bell County goes 8.1 hours a year without power, the 141st most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Five Wells Solar Center - Hybrid (outlined) and other plants in Bell County, shaded. 30.999, -97.259.
Plant facts
- Operator
- Five Wells Solar Center, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Bell County, TX
- EIA plant ID
- 66420
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| FWSOL | Solar Photovoltaic | 355 MW | 2023 | – |
| FWBAT | Batteries | 263 MW · 250 MWh | 2024 | – |
Nearby
Other plants in Bell County
Questions
Five Wells Solar Center - Hybrid, answered
How much power does Five Wells Solar Center - Hybrid produce?
Five Wells Solar Center - Hybrid has 618 MW of capacity from 2 generators. In 2025 it generated 723 GWh, 13% of the most it could have made running flat out all year (its capacity factor).
How many homes does Five Wells Solar Center - Hybrid power?
Its 2025 output of 723 GWh equals the yearly electricity use of about 54,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Five Wells Solar Center - Hybrid?
Five Wells Solar Center - Hybrid is in Bell County, Texas, at about 30.999°, -97.259°. It is one of 12 power plants of 1 MW or more in the county. The average electricity customer in Bell County goes 8.1 hours a year without power, the 141st most of 240 counties in Texas. The county's page has the full outage record.
Who operates Five Wells Solar Center - Hybrid?
It is operated by Five Wells Solar Center, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Five Wells Solar Center - Hybrid open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.