Wind power plant · Mitchell, TX
Loraine Windpark Project LLC
Loraine Windpark Project LLC is a 150 MW wind power plant in Mitchell County, Texas, operated by Loraine Windpower Project. Its oldest generator still running came online in 2009. In 2025 it generated 328 GWh, about what 25,000 average Texas homes use in a year.
Loraine Windpark Project LLC in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 150th largest, about 0.3% of the state's 45 GW of wind capacity.
Mitchell County has 3 power plants of 1 MW or more with 688 MW in all; Loraine Windpark Project LLC is 22% of that.
Its capacity factor of 25% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Mitchell County goes 13 hours a year without power, the 90th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Loraine Windpark Project LLC (outlined) and other plants in Mitchell County, shaded. 32.438, -100.744.
Plant facts
- Operator
- Loraine Windpower Project
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Mitchell County, TX
- EIA plant ID
- 57303
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| LWG1 | Onshore Wind Turbine | 75 MW | 2009 | – |
| LWG2 | Onshore Wind Turbine | 75 MW | 2009 | – |
Nearby
Other plants in Mitchell County
Questions
Loraine Windpark Project LLC, answered
How much power does Loraine Windpark Project LLC produce?
Loraine Windpark Project LLC has 150 MW of capacity from 2 generators. In 2025 it generated 328 GWh, 25% of the most it could have made running flat out all year (its capacity factor).
How many homes does Loraine Windpark Project LLC power?
Its 2025 output of 328 GWh equals the yearly electricity use of about 25,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Loraine Windpark Project LLC?
Loraine Windpark Project LLC is in Mitchell County, Texas, at about 32.438°, -100.744°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Mitchell County goes 13 hours a year without power, the 90th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Loraine Windpark Project LLC?
It is operated by Loraine Windpower Project (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Loraine Windpark Project LLC open?
Its oldest generator still running came online in 2009.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.