AI data center · Fayetteville, Georgia

Microsoft Fairwater Atlanta

Microsoft's AI campus in Fayette County. It draws about 636 MW today and is planned to reach 859 MW by June 2026.

Power now636 MWAs of Jun 14, 2026
Planned peak859 MWJune 2026
Compute769kH100-equivalent chips now
Capital cost$24BSo far, 2025 dollars

Latest look · Jun 14, 2026

What the satellite shows

Building 3 and 4 are operational.

Build-out

Power, month by month

0 MW200 MW400 MW600 MW800 MW1 GW202420252026
Power drawn by Microsoft Fairwater Atlanta, from Epoch AI's dated observations.
0 MW200 MW400 MW600 MW800 MW1 GW202420252026
Power drawn by Microsoft Fairwater Atlanta, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Microsoft
Used by
OpenAI (likely), Microsoft (likely)
Project
Microsoft AI WAN
Energy companies
Georgia Power
Chips
B200
Address
1435 Hwy 54 W, Fayetteville, GA 30214
County
Fayette County

Where

On the map of Georgia

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Timeline

Every observation

DateWhat Epoch AI sawPower
Jun 14, 2026Building 3 and 4 are operational.859 MW
May 15, 2026Building 4 still has some equipment strewn around the perimeter, so we think it is still going through commissioning. Two new buildings at the campus have shells underway, but we don't know if Microsoft is the tenant for those.433 MW
Feb 13, 2026Building 4 roof is complete and all mechanical equipment appears to be installed. However, there is still a lot of construction activity around the building.433 MW
Oct 14, 2025Building 1 and 2 are operational. Building 1 looked operational sooner, but the buildings are paired in the Fairwater design. The roof of Building 4 is almost complete, while mechanical equipment is still being installed.433 MW
Apr 9, 2023Land clearing begins for southern part (Building 1-2)–

How much power does Microsoft Fairwater Atlanta use?

About 636 MW as of Jun 14, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 859 MW in its build plans by June 2026. Running all year, 636 MW would use about 5.6 TWh.

Who owns Microsoft Fairwater Atlanta?

Microsoft; used by OpenAI (likely), Microsoft (likely). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Microsoft Fairwater Atlanta?

In Fayette County, the average customer is without power about 2.1 hours in a typical year in this site's outage record, with 7 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.