AI data center · Dalton, Georgia

CoreWeave Dalton 1 & 2

CoreWeave's AI campus in Whitfield County. It draws about 28 MW today and is planned to reach 40 MW by February 2026.

Power now28 MWAs of Feb 20, 2026
Planned peak40 MWFebruary 2026
Compute32kH100-equivalent chips now
Capital cost$1.1BSo far, 2025 dollars

Latest look · Feb 20, 2026

What the satellite shows

Building 1 is operational, given it was announced completed 4 months ago and looks completed in satellite imagery. All cooling/mechanical rows are installed, with no obvious active building construction visible.

Build-out

Power, month by month

0 MW10 MW20 MW30 MW40 MW50 MW20252026
Power drawn by CoreWeave Dalton 1 & 2, from Epoch AI's dated observations.
0 MW10 MW20 MW30 MW40 MW50 MW20252026
Power drawn by CoreWeave Dalton 1 & 2, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
CoreWeave
Used by
OpenAI (speculative)
Chips
B300
Address
2205 Industrial South Rd, Dalton, GA, 30721
County
Whitfield County

Where

On the map of Georgia

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Thomas A Smith Energy Facility● Natural gas1.19 GW2 mi
Dalton 2● Solar7 MW1.2 mi
Murray Treadwell Farms● Solar3 MW8.8 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Feb 20, 2026Building 1 is operational, given it was announced completed 4 months ago and looks completed in satellite imagery. All cooling/mechanical rows are installed, with no obvious active building construction visible.40 MW
Aug 29, 2025Based on Satellite imagery, Dalton 1 is still under construction. The building appears mostly roofed except for the entrance area, and there are no cooling units or backup generators installed yet.–
May 1, 2025Core Scientific investor presentation clearly shows Dalton 1 with a cleared pad on this month for construction. Source: https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001140361-25-039864/0001140361-25-039864.pdf–
Jun 3, 2024According to a few sources, Core Scientific announced that they're rebuilding their existing Dalton 1 (and we're assuming 2) datacenter to run AI using CoreWeave's GPUs, of which contract was first signed on this date. According to the press release, "The site modifications are expected to commence early in the second half of 2024 and achieve operational status in the first half of 2025."–

How much power does CoreWeave Dalton 1 & 2 use?

About 28 MW as of Feb 20, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 40 MW in its build plans by February 2026. Running all year, 28 MW would use about 0.2 TWh.

Who owns CoreWeave Dalton 1 & 2?

CoreWeave; used by OpenAI (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around CoreWeave Dalton 1 & 2?

In Whitfield County, the average customer is without power about 2.0 hours in a typical year in this site's outage record, with 4 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near CoreWeave Dalton 1 & 2?

3 plants within 15 miles total about 1.20 GW; the largest is Thomas A Smith Energy Facility (1.19 GW, natural gas), 2 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.