AI data center · Berwick, Pennsylvania
AWS Berwick
Amazon's AI campus in Luzerne County. It draws about 108 MW today and is planned to reach 212 MW by August 2027.
Latest look · Aug 1, 2026
What the satellite shows
Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Amazon
- Used by
- Anthropic (speculative)
- Project
- Project Rainier (speculative)
- Chips
- Trainium2
- Water use
- 0.13 million gallons a day (Epoch AI estimate)
- Address
- 1125 Electron Ave, Berwick, PA 18603
- County
- Luzerne County
Where
On the map of Pennsylvania
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| TalenEnergy Susquehanna | ● Nuclear | 2.53 GW | 0.6 mi |
| Moxie Freedom Generation Plant | ● Natural gas | 1.10 GW | 2.2 mi |
| Hazelton | ● Natural gas | 172 MW | 12 mi |
| Hunlock Power Station | ● Natural gas | 146 MW | 8.9 mi |
| Hunlock Unit 4 | ● Natural gas | 44 MW | 9.1 mi |
| Hazle Spindle | ● Storage | 20 MW | 10.5 mi |
| Romark PA Solar | ● Solar | 2 MW | 11.6 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Aug 1, 2026 | Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference. | 139 MW |
| May 5, 2026 | Buildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several additional building shells and pads are still in construction, but none are assumed operational due to all the construction work visible. This is based on satellite imagery from this date. | 102 MW |
| Mar 12, 2026 | The SRBC increases approved water use from 0.060 MGD to 0.129 MGD. This supports that some expansion is happening, but does not explicitly prove a third operational building. | 102 MW |
| Jan 7, 2026 | Building 2 operational estimate. This is based on the progress visible in the September 2025 image. The DEP also issues an air plan approval to add 48 more emergency generators on this date. | 102 MW |
| Sep 9, 2025 | Building 1 operational estimate. According to Google Earth Satellite Imagery from this date, Building 1 appears structurally complete and likely operational, while Building 2 is still missing two generators. | 66 MW |
| Jun 1, 2024 | Building 1 fit out and related construction begins under Amazon, based on the Susquehanna River Basin Commission (SRBC) schedule. | – |
| Mar 4, 2024 | AWS acquires the Cumulus/Talen building campus for $650M. | – |
| Jan 17, 2023 | Cumulus completes a 48 MW, 300,000 sq ft powered shell for the first data center at the Susquehanna campus. The shell is available for lease, with the campus still awaiting its first tenant and commercial operations. | – |
| Jul 1, 2021 | Land clearing begins. Talen Energy reported on July 12, 2021 that site-preparation permits had already been obtained and site work was underway, while permits for construction of the first building were still being pursued. We model land clearing as starting from the beginning of the month. | – |
Plus 1 projected step to August 2027, from Epoch AI's reading of the build plans.
How much power does AWS Berwick use?
About 108 MW as of Aug 1, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 212 MW in its build plans by August 2027. Running all year, 108 MW would use about 0.9 TWh.
Who owns AWS Berwick?
Amazon; used by Anthropic (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around AWS Berwick?
In Luzerne County, the average customer is without power about 2.5 hours in a typical year in this site's outage record, with 0 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near AWS Berwick?
7 plants within 15 miles total about 4.02 GW; the largest is TalenEnergy Susquehanna (2.53 GW, nuclear), 0.6 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- NYT reporting that one of the Project Rainier sites may be in Pennsylvania
- Talen SEC filing detailing the $650M sale of the Cumulus data center campus to AWS
- Pennsylvania PUC filing describing the planned 16-building AWS data center development
- SRBC filing covering AWS campus expansion and water-use plans
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.