AI data center · Berwick, Pennsylvania

AWS Berwick

Amazon's AI campus in Luzerne County. It draws about 108 MW today and is planned to reach 212 MW by August 2027.

Power now108 MWAs of Aug 1, 2026
Planned peak212 MWAugust 2027
Compute81kH100-equivalent chips now
Capital cost$4.1BSo far, 2025 dollars

Latest look · Aug 1, 2026

What the satellite shows

Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.

Build-out

Power, month by month

0 MW50 MW100 MW150 MW200 MW250 MW202220232024202520262027Today
Power drawn by AWS Berwick, from Epoch AI's dated observations and (hatched) its projections.
0 MW50 MW100 MW150 MW200 MW250 MW202220232024202520262027Today
Power drawn by AWS Berwick, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Amazon
Used by
Anthropic (speculative)
Project
Project Rainier (speculative)
Chips
Trainium2
Water use
0.13 million gallons a day (Epoch AI estimate)
Address
1125 Electron Ave, Berwick, PA 18603
County
Luzerne County

Where

On the map of Pennsylvania

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
TalenEnergy Susquehanna● Nuclear2.53 GW0.6 mi
Moxie Freedom Generation Plant● Natural gas1.10 GW2.2 mi
Hazelton● Natural gas172 MW12 mi
Hunlock Power Station● Natural gas146 MW8.9 mi
Hunlock Unit 4● Natural gas44 MW9.1 mi
Hazle Spindle● Storage20 MW10.5 mi
Romark PA Solar● Solar2 MW11.6 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Aug 1, 2026Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.139 MW
May 5, 2026Buildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several additional building shells and pads are still in construction, but none are assumed operational due to all the construction work visible. This is based on satellite imagery from this date.102 MW
Mar 12, 2026The SRBC increases approved water use from 0.060 MGD to 0.129 MGD. This supports that some expansion is happening, but does not explicitly prove a third operational building.102 MW
Jan 7, 2026Building 2 operational estimate. This is based on the progress visible in the September 2025 image. The DEP also issues an air plan approval to add 48 more emergency generators on this date.102 MW
Sep 9, 2025Building 1 operational estimate. According to Google Earth Satellite Imagery from this date, Building 1 appears structurally complete and likely operational, while Building 2 is still missing two generators.66 MW
Jun 1, 2024Building 1 fit out and related construction begins under Amazon, based on the Susquehanna River Basin Commission (SRBC) schedule.–
Mar 4, 2024AWS acquires the Cumulus/Talen building campus for $650M.–
Jan 17, 2023Cumulus completes a 48 MW, 300,000 sq ft powered shell for the first data center at the Susquehanna campus. The shell is available for lease, with the campus still awaiting its first tenant and commercial operations.–
Jul 1, 2021Land clearing begins. Talen Energy reported on July 12, 2021 that site-preparation permits had already been obtained and site work was underway, while permits for construction of the first building were still being pursued. We model land clearing as starting from the beginning of the month.–

Plus 1 projected step to August 2027, from Epoch AI's reading of the build plans.

How much power does AWS Berwick use?

About 108 MW as of Aug 1, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 212 MW in its build plans by August 2027. Running all year, 108 MW would use about 0.9 TWh.

Who owns AWS Berwick?

Amazon; used by Anthropic (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around AWS Berwick?

In Luzerne County, the average customer is without power about 2.5 hours in a typical year in this site's outage record, with 0 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near AWS Berwick?

7 plants within 15 miles total about 4.02 GW; the largest is TalenEnergy Susquehanna (2.53 GW, nuclear), 0.6 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.