AI data center · New Albany, Ohio
AWS New Albany
Amazon's AI campus in Licking County. It draws about 213 MW today and is planned to reach 405 MW by July 2027.
Latest look · May 18, 2026
What the satellite shows
Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Amazon
- Chips
- Trainium2, H100, H200, B200
- Address
- 13360 Miller Rd NW
- County
- Licking County
Where
On the map of Ohio
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Denison Solar Array | ● Solar | 2 MW | 12.1 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| May 18, 2026 | Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted. | 255 MW |
| Mar 12, 2026 | Middle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on satellite imagery, northern campus Buildings 1-3 appear in late construction, with all roofs complete but nearby generator/cooling equipment still being installed for buildings 2-3. Building 4 is still early in construction. Eastern campus Buildings 5-9 appear complete and operational as expected. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed. | 255 MW |
| Dec 1, 2024 | Buildings 5-9 (eastern campus) operational. New Albany’s Dec. 2024 report lists AWS partial occupancy for 5 buildings at the eastern campus. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed. The full IT power is much higher than 113 MW. | 136 MW |
| Jun 1, 2022 | Land clearing begins for Buildings 5-9 (eastern campus). | – |
Plus 1 projected step to July 2027, from Epoch AI's reading of the build plans.
How much power does AWS New Albany use?
About 213 MW as of May 18, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 405 MW in its build plans by July 2027. Running all year, 213 MW would use about 1.9 TWh.
Who owns AWS New Albany?
Amazon. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around AWS New Albany?
In Licking County, the average customer is without power about 3.5 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near AWS New Albany?
One plant is within 15 miles: Denison Solar Array (2 MW, solar), 12.1 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- City of New Albany Project Updates
- New Albany Community Development Report - Dec. 2024
- New Albany Community Development Report - Aug. 2025
- Article reporting first signing of the project
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.