AI data center · New Albany, Ohio

AWS New Albany

Amazon's AI campus in Licking County. It draws about 213 MW today and is planned to reach 405 MW by July 2027.

Power now213 MWAs of May 18, 2026
Planned peak405 MWJuly 2027
Compute201kH100-equivalent chips now
Capital cost$8.1BSo far, 2025 dollars

Latest look · May 18, 2026

What the satellite shows

Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW500 MW20232024202520262027Today
Power drawn by AWS New Albany, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW400 MW500 MW20232024202520262027Today
Power drawn by AWS New Albany, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Amazon
Chips
Trainium2, H100, H200, B200
Address
13360 Miller Rd NW
County
Licking County

Where

On the map of Ohio

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Denison Solar Array● Solar2 MW12.1 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
May 18, 2026Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.255 MW
Mar 12, 2026Middle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on satellite imagery, northern campus Buildings 1-3 appear in late construction, with all roofs complete but nearby generator/cooling equipment still being installed for buildings 2-3. Building 4 is still early in construction. Eastern campus Buildings 5-9 appear complete and operational as expected. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed.255 MW
Dec 1, 2024Buildings 5-9 (eastern campus) operational. New Albany’s Dec. 2024 report lists AWS partial occupancy for 5 buildings at the eastern campus. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed. The full IT power is much higher than 113 MW.136 MW
Jun 1, 2022Land clearing begins for Buildings 5-9 (eastern campus).–

Plus 1 projected step to July 2027, from Epoch AI's reading of the build plans.

How much power does AWS New Albany use?

About 213 MW as of May 18, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 405 MW in its build plans by July 2027. Running all year, 213 MW would use about 1.9 TWh.

Who owns AWS New Albany?

Amazon. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around AWS New Albany?

In Licking County, the average customer is without power about 3.5 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near AWS New Albany?

One plant is within 15 miles: Denison Solar Array (2 MW, solar), 12.1 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.