AI data center · Lordstown, Ohio

OpenAI Stargate Lordstown

Softbank's AI campus in Trumbull County. It is not drawing power yet and is planned to reach 300 MW by March 2027.

Power now–As of Jul 30, 2026
Planned peak300 MWMarch 2027
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Jul 30, 2026

What the satellite shows

Active construction visible on and around the datacenter, with the roofing mostly in place. This is based on satellite imagery. No buildings operational yet.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW20262027Today
Power drawn by OpenAI Stargate Lordstown, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW400 MW20262027Today
Power drawn by OpenAI Stargate Lordstown, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Softbank
Used by
OpenAI
Project
Stargate
Chips
Rubin
Address
2300 Hallock Young Rd, Warren, OH 44481
County
Trumbull County

Where

On the map of Ohio

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Trumbull Energy Center● Natural gas977 MW1.6 mi
Middletown- Ohio● Natural gas962 MW1.7 mi
Niles Power Plant● Oil27 MW7.2 mi
Clevelandcliffs Warren● Other13 MW5.8 mi
Niles RTO BTM● Oil11 MW7 mi
KSU Trumbull● Solar1 MW9.6 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jul 30, 2026Active construction visible on and around the datacenter, with the roofing mostly in place. This is based on satellite imagery. No buildings operational yet.–
Feb 27, 2026Still no visible construction, although construction within preexisting facilities–
Oct 12, 2025Land clearing begins in the front of the site (the side facing the Ohio Turnpike), clearing away a parking lot and solar array–

Plus 1 projected step to March 2027, from Epoch AI's reading of the build plans.

How much power does OpenAI Stargate Lordstown use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 300 MW by March 2027.

Who owns OpenAI Stargate Lordstown?

Softbank; used by OpenAI. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around OpenAI Stargate Lordstown?

In Trumbull County, the average customer is without power about 8.4 hours in a typical year in this site's outage record, with 18 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near OpenAI Stargate Lordstown?

6 plants within 15 miles total about 1.99 GW; the largest is Trumbull Energy Center (977 MW, natural gas), 1.6 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.