Meta's AI campus in Franklin County. It draws about 471 MW today and is planned to reach 1.33 GW by July 2028.
Latest look · Aug 31, 2026
What the satellite shows
Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power plant (about 69% of the 200 MW nameplate capacity), and Buildings 7-10 roof vents are bright on infrared while Buildings 11-12 vents are not. That's 4/6 buildings operating, implying about 67% of capacity, which is consistent with 69% of the power plant operating. In the north, Buildings 16-27 (tents) look to be in a completed state. Each northern set of 6 tents still awaits to be connected to one of the corresponding power plants to become operational. Drone video from August 19th shows no turbines operating at Socrates North, though there are 3 small diesel generators operating. Building 13 (Vantage) is still under construction, we estimate another 3 months before operability.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Meta
- Used by
- Meta
- Project
- Prometheus
- Energy companies
- Williams, American Electric Power
- Chips
- B300
- Address
- 1 Community Cir, New Albany, OH 43054
- County
- Franklin County (approximate)
Where
On the map of Ohio
Placed at the centre of New Albany, as no address could be matched, so the dot and the county are approximate.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Denison Solar Array | ● Solar | 2 MW | 13.7 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Aug 31, 2026 | Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power plant (about 69% of the 200 MW nameplate capacity), and Buildings 7-10 roof vents are bright on infrared while Buildings 11-12 vents are not. That's 4/6 buildings operating, implying about 67% of capacity, which is consistent with 69% of the power plant operating. In the north, Buildings 16-27 (tents) look to be in a completed state. Each northern set of 6 tents still awaits to be connected to one of the corresponding power plants to become operational. Drone video from August 19th shows no turbines operating at Socrates North, though there are 3 small diesel generators operating. Building 13 (Vantage) is still under construction, we estimate another 3 months before operability. | 612 MW |
| May 18, 2026 | Building 7-11 (Meta tents) look structurally complete but not operational, given there is still construction activity, including at the adjacent Socrates South power plant. Northern tents (Buildings 16-27) are all roofed except for 21 and 27. | 478 MW |
| Mar 12, 2026 | The Socrates South power plant to the right of Buildings 7-12 now has 10 natural gas turbines in place, judging by the number of exhaust stacks. Battery backup has been installed nearby. To the north, a new section of tent buildings has begun east of Buildings 16-20. | 478 MW |
| Jan 18, 2026 | Buildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of power or cooling equipment lining their right side which are not fully installed. Building 14 has chillers installed. Buildings 16-20 roofs are complete. The Socrates South power plant to the right of Buildings 7-11 has 7 gas turbines in place, judging by the exhaust stacks. | 478 MW |
| Oct 14, 2025 | Building 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18 roof is complete. The on-site power at Socrates South and Socrates North has some outlines of gas turbines, to be installed later. | 99 MW |
| Sep 20, 2025 | Building 4 operational. Based on our default estimate of roof-to-operational time. | – |
| Jun 1, 2025 | Roof complete on Building 5 (QTS-owned). In the northernmost area, land clearing begins on a new Meta site for Buildings 16-20. Building 1 still has construction work around the building and cooling equipment, so it's unlikely to be operational. | – |
| Apr 14, 2022 | Land clearing begins for Building 1-2 | – |
Plus 5 projected steps to July 2028, from Epoch AI's reading of the build plans.
How much power does Meta Prometheus use?
About 471 MW as of Aug 31, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 1.33 GW in its build plans by July 2028. Running all year, 471 MW would use about 4.1 TWh.
Who owns Meta Prometheus?
Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Meta Prometheus?
In Franklin County, the average customer is without power about 6.5 hours in a typical year in this site's outage record, with 1 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Meta Prometheus?
One plant is within 15 miles: Denison Solar Array (2 MW, solar), 13.7 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Meta blog post with details on Prometheus
- New Albany Business Park land use map
- Letter on Socrates South Power Generation Project
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.