Google Lancaster

Google's AI campus in Fairfield County. It draws about 137 MW today and is planned to reach 164 MW by October 2025.

Power now137 MWAs of Mar 12, 2026
Planned peak164 MWOctober 2025
Compute130kH100-equivalent chips now
Capital cost$5.2BSo far, 2025 dollars

Latest look · Mar 12, 2026

What the satellite shows

At this point, Building 1 and 2 have since already been operational. Additionally, there is visible steam showing clear evidence of operational for both before this date.

Build-out

Power, month by month

0 MW50 MW100 MW150 MW200 MW20222023202420252026
Power drawn by Google Lancaster, from Epoch AI's dated observations.
0 MW50 MW100 MW150 MW200 MW20222023202420252026
Power drawn by Google Lancaster, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Google
Chips
TPU v5e, TPU v6e
Address
105 Whiley Rd, Lancaster, OH 43130
County
Fairfield County

Where

On the map of Ohio

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Timeline

Every observation

DateWhat Epoch AI sawPower
Mar 12, 2026At this point, Building 1 and 2 have since already been operational. Additionally, there is visible steam showing clear evidence of operational for both before this date.164 MW
Oct 31, 2025Building 2 operational. This is supported by the state of Building 2 a month prior, which is entirely complete outside of some equipment that was removed later on.164 MW
Sep 11, 2025Building 2 is close to completion. Structurally it is already complete, but there is still some equipment strewn around the building that suggests commissioning is ongoing.82 MW
Jan 1, 2024Building 1 operational. This is estimated based on construction progress in October 2023. This also corresponds to a 2023 article where a Google spokesperson says that the "the Lancaster data center will open later this year".82 MW
Oct 1, 2021Land clearing in progress for the site–

How much power does Google Lancaster use?

About 137 MW as of Mar 12, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 164 MW in its build plans by October 2025. Running all year, 137 MW would use about 1.2 TWh.

Who owns Google Lancaster?

Google. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Lancaster?

In Fairfield County, the average customer is without power about 5.1 hours in a typical year in this site's outage record, with 17 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.