AI data center · Bowling Green, Ohio
Meta Bowling Green
Meta's AI campus in Wood County. It is not drawing power yet and is planned to reach 570 MW by January 2028.
Latest look · Jul 30, 2026
What the satellite shows
Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the Apollo Power Generation Project (a BTM power plant built just to the east of the data center) is in progress, with foundations poured and generation equipment being set in place.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Meta
- Used by
- Meta
- Energy companies
- Williams
- Chips
- B300, Rubin
- Address
- 12356 Middleton Pike, Bowling Green, OH 43402
- County
- Wood County
Where
On the map of Ohio
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Troy Energy LLC | ● Natural gas | 796 MW | 9.2 mi |
| Bowling Green Generating Station | ● Natural gas | 50 MW | 4.2 mi |
| Bowling Green Peaking | ● Natural gas | 32 MW | 4.8 mi |
| DG AMP Solar Bowling Green | ● Solar | 20 MW | 5.1 mi |
| Bowling Green Energy Storage Project | ● Storage | 12 MW | 5.4 mi |
| Toledo Ref Power Recovery Train | ● Oil | 6 MW | 13.8 mi |
| Genoa Diesel Generating Station | ● Oil | 6 MW | 14.7 mi |
| Martin Marietta Wind Project | ● Wind | 5 MW | 13.9 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jul 30, 2026 | Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the Apollo Power Generation Project (a BTM power plant built just to the east of the data center) is in progress, with foundations poured and generation equipment being set in place. | – |
| Feb 14, 2026 | Buildings 1 and 2 under construction. Building 1's chillers are almost all in place, while only half of Building 2's are. Optimus substation, which is the substation on site, and the expansion of Dowling Substation, an existing substation to the northeast of the data center, appear complete. | – |
| Nov 1, 2024 | Land clearing begins. | – |
Plus 3 projected steps to January 2028, from Epoch AI's reading of the build plans.
How much power does Meta Bowling Green use?
It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 570 MW by January 2028.
Who owns Meta Bowling Green?
Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Meta Bowling Green?
In Wood County, the average customer is without power about 1.4 hours in a typical year in this site's outage record, with 1 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Meta Bowling Green?
8 plants within 15 miles total about 942 MW; the largest is Troy Energy LLC (796 MW, natural gas), 9.2 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Meta letter to Middleton Township
- Construction notice for new transmission lines to data center substation
- Ohio Power Siting Board announcement
- Apollo Power Generation Project Letter of Notice Appendix A, with a project timeline
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.