AI data center · Columbus, Ohio

Google Columbus

Google's AI campus in Franklin County. It draws about 303 MW today and is planned to reach 464 MW by July 2027.

Power now303 MWAs of Aug 5, 2026
Planned peak464 MWJuly 2027
Compute332kH100-equivalent chips now
Capital cost$11BSo far, 2025 dollars

Latest look · Aug 5, 2026

What the satellite shows

Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.

Build-out

Power, month by month

0 MW200 MW400 MW600 MW202220232024202520262027Today
Power drawn by Google Columbus, from Epoch AI's dated observations and (hatched) its projections.
0 MW200 MW400 MW600 MW202220232024202520262027Today
Power drawn by Google Columbus, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Google
Used by
Google DeepMind (speculative)
Chips
TPU v5e, TPU v5p, TPU v6e, TPU v7
Address
5076 S High St, Columbus, OH 43207
County
Franklin County

Where

On the map of Ohio

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Darby Power, LLC● Natural gas564 MW13.8 mi
Tosoh SMD● Natural gas4 MW3.3 mi
Renick Run Pumping Station 03-04● Oil3 MW4.7 mi
Jackson Pike WWTP Cogen Engines● Biomass3 MW3.5 mi
PS ST-8 Engine No 1● Oil2 MW7.3 mi
Dodge Park Engine No 1● Oil2 MW6.3 mi
ST-1/1A Engine No 1● Oil1 MW6.2 mi
3100 Valleyview Drive● Solar1 MW6.7 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Aug 5, 2026Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.364 MW
May 1, 2026Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.364 MW
Feb 21, 2026Buildings 1-3 are visibly operational, with steam coming out of the cooling towers. Meanwhile Building 4 is extremely close to completion, with all backup generators complete with only 3 cooling towers missing their fans. ~1/2 the generators are installed for Building 5, and the roof is mostly complete (starting to install the final white layer, with the actual roof structure already complete).260 MW
Oct 1, 2025Building 3 operational. Surrounding roads finished, no more visible construction.260 MW
Mar 1, 2025Building 2 operational. Parking complete, no more visible construction.156 MW
Apr 1, 2024Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building 3.78 MW
Jul 1, 2023Building 2 foundation work begins. Building 1 generators seem complete, cooling towers still under construction.–
Oct 1, 2021Land clearing begins on the eastern half of the site, for Buildings 1-2–

Plus 1 projected step to July 2027, from Epoch AI's reading of the build plans.

How much power does Google Columbus use?

About 303 MW as of Aug 5, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 464 MW in its build plans by July 2027. Running all year, 303 MW would use about 2.7 TWh.

Who owns Google Columbus?

Google; used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Columbus?

In Franklin County, the average customer is without power about 6.5 hours in a typical year in this site's outage record, with 1 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google Columbus?

8 plants within 15 miles total about 579 MW; the largest is Darby Power, LLC (564 MW, natural gas), 13.8 miles away. Nearness does not mean it supplies the campus.