AI data center · New Albany, Ohio
Google New Albany
Google's AI campus in Licking County. It draws about 333 MW today and is planned to reach 400 MW by October 2025.
Latest look · May 18, 2026
What the satellite shows
Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Used by
- Google DeepMind (speculative)
- Chips
- TPU v5e, TPU v5p, TPU v6e
- Water use
- 0.97 million gallons a day (Epoch AI estimate)
- Address
- 1101 Beech Rd SW, New Albany, OH 43054
- County
- Licking County
Where
On the map of Ohio
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Denison Solar Array | ● Solar | 2 MW | 12.5 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| May 18, 2026 | Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational. | 400 MW |
| Mar 12, 2026 | Building 5 has more cooling towers installed but not complete, and the roof is almost complete. | 400 MW |
| Jan 18, 2026 | Water vapor from cooling towers is present across Building 1-4, confirming their operation. Building 5 roof is still incomplete, but most backup generators and 5 cooling towers have been installed. | 400 MW |
| Oct 14, 2025 | Building 4 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 5 roof is half complete. About half of the backup generators are in place. One cooling tower is partly built. | 400 MW |
| Jun 1, 2025 | Building 3 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 4 still has some work around the cooling towers. Work is underway on Building 5 - some walls and a few backup generators are in place. | 267 MW |
| Sep 13, 2024 | Building 2 is operational. Google Earth imagery shows 6 cooling towers installed as of 2024-04-20, and a final 7th unit appeared as of 2024-09-13, with minimal construction around the building. Building 3 roof is also complete. | 173 MW |
| Apr 20, 2024 | Building 1 is operational. Based on ~7 months since roof being completed, and cooling towers being installed sometime within that period. Building 2 roof is complete. | 80 MW |
| Mar 1, 2021 | Land clearing begins. | – |
How much power does Google New Albany use?
About 333 MW as of May 18, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 400 MW in its build plans by October 2025. Running all year, 333 MW would use about 2.9 TWh.
Who owns Google New Albany?
Google; used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google New Albany?
In Licking County, the average customer is without power about 3.5 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google New Albany?
One plant is within 15 miles: Denison Solar Array (2 MW, solar), 12.5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.