AI data center · New Albany, Ohio

Google New Albany

Google's AI campus in Licking County. It draws about 333 MW today and is planned to reach 400 MW by October 2025.

Power now333 MWAs of May 18, 2026
Planned peak400 MWOctober 2025
Compute324kH100-equivalent chips now
Capital cost$13BSo far, 2025 dollars

Latest look · May 18, 2026

What the satellite shows

Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW500 MW20222023202420252026
Power drawn by Google New Albany, from Epoch AI's dated observations.
0 MW100 MW200 MW300 MW400 MW500 MW20222023202420252026
Power drawn by Google New Albany, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Google
Used by
Google DeepMind (speculative)
Chips
TPU v5e, TPU v5p, TPU v6e
Water use
0.97 million gallons a day (Epoch AI estimate)
Address
1101 Beech Rd SW, New Albany, OH 43054
County
Licking County

Where

On the map of Ohio

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Denison Solar Array● Solar2 MW12.5 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
May 18, 2026Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational.400 MW
Mar 12, 2026Building 5 has more cooling towers installed but not complete, and the roof is almost complete.400 MW
Jan 18, 2026Water vapor from cooling towers is present across Building 1-4, confirming their operation. Building 5 roof is still incomplete, but most backup generators and 5 cooling towers have been installed.400 MW
Oct 14, 2025Building 4 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 5 roof is half complete. About half of the backup generators are in place. One cooling tower is partly built.400 MW
Jun 1, 2025Building 3 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 4 still has some work around the cooling towers. Work is underway on Building 5 - some walls and a few backup generators are in place.267 MW
Sep 13, 2024Building 2 is operational. Google Earth imagery shows 6 cooling towers installed as of 2024-04-20, and a final 7th unit appeared as of 2024-09-13, with minimal construction around the building. Building 3 roof is also complete.173 MW
Apr 20, 2024Building 1 is operational. Based on ~7 months since roof being completed, and cooling towers being installed sometime within that period. Building 2 roof is complete.80 MW
Mar 1, 2021Land clearing begins.–

How much power does Google New Albany use?

About 333 MW as of May 18, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 400 MW in its build plans by October 2025. Running all year, 333 MW would use about 2.9 TWh.

Who owns Google New Albany?

Google; used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google New Albany?

In Licking County, the average customer is without power about 3.5 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google New Albany?

One plant is within 15 miles: Denison Solar Array (2 MW, solar), 12.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.