Natural gas power plant · Wood, OH

Bowling Green Peaking

Bowling Green Peaking is a 32 MW natural gas power plant in Wood County, Ohio, operated by American Mun Power-Ohio, Inc. Its oldest generator still running came online in 2000. In 2025 it generated 2.3 GWh, about what 219 average Ohio homes use in a year.

Capacity32 MWNameplate, September 2026
Generated2.3 GWhIn 2025
Capacity factor1%Share of the most it could make, 2025
Generators1Oldest from 2000

Bowling Green Peaking in context

Among the 48 natural gas plants in Ohio in the EIA's inventory, it is the 34th largest, about 0.2% of the state's 20 GW of natural gas capacity.

Wood County has 8 power plants of 1 MW or more with 915 MW in all; Bowling Green Peaking is 3% of that and the 3rd largest of 3 natural gas plants there.

Its capacity factor of 1% in 2025 is lower than the 23% typical for natural gas plants across the US.

The average electricity customer in Wood County goes 1.4 hours a year without power, the 87th most of 88 counties in Ohio. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0123420182019202020212022202320242025GWh 2
0123420192021202320252

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Bowling Green Peaking (outlined) and other plants in Wood County, shaded. 41.388, -83.640.

Plant facts

Operator
American Mun Power-Ohio, Inc
Sector
Electric Utility
Grid operator
PJM
County
Wood County, OH
EIA plant ID
7783
Where Ohio's power comes from → Ohio power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Natural Gas Fired Combustion Turbine 32 MW 2000 –

Nearby

Other plants in Wood County

Questions

Bowling Green Peaking, answered

How much power does Bowling Green Peaking produce?

Bowling Green Peaking has 32 MW of capacity from one generator. In 2025 it generated 2.3 GWh, 1% of the most it could have made running flat out all year (its capacity factor).

How many homes does Bowling Green Peaking power?

Its 2025 output of 2.3 GWh equals the yearly electricity use of about 219 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Bowling Green Peaking?

Bowling Green Peaking is in Wood County, Ohio, at about 41.388°, -83.640°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Wood County goes 1.4 hours a year without power, the 87th most of 88 counties in Ohio. The county's page has the full outage record.

Who operates Bowling Green Peaking?

It is operated by American Mun Power-Ohio, Inc (EIA sector: Electric Utility), and it feeds PJM Interconnection.

When did Bowling Green Peaking open?

Its oldest generator still running came online in 2000.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.