AI data center · The Dalles, Oregon
Google The Dalles
Google's AI campus in Wasco County. It draws about 154 MW today and is planned to reach 185 MW by April 2026.
Latest look · Apr 29, 2026
What the satellite shows
Building 2 is estimated to be operational, based on all external equipment being installed, and ordinary cars parked by the building.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Chips
- TPU v6e, TPU v5p, TPU v5e, TPU v7
- Address
- 3500 River Rd, The Dalles, OR
- County
- Wasco County
Where
On the map of Oregon
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| The Dalles | ● Hydro | 1.82 GW | 3.4 mi |
| Dalles Dam North Fishway Project | ● Hydro | 7 MW | 3.3 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Apr 29, 2026 | Building 2 is estimated to be operational, based on all external equipment being installed, and ordinary cars parked by the building. | 185 MW |
| Mar 7, 2025 | Building 1 is estimated to be operational, based on all external equipment being installed. | 93 MW |
| Mar 1, 2023 | Land clearing begins. | – |
How much power does Google The Dalles use?
About 154 MW as of Apr 29, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 185 MW in its build plans by April 2026. Running all year, 154 MW would use about 1.3 TWh.
Who owns Google The Dalles?
Google. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google The Dalles?
In Wasco County, the average customer is without power about 1.7 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google The Dalles?
2 plants within 15 miles total about 1.83 GW; the largest is The Dalles (1.82 GW, hydro), 3.4 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Permit confirming this is a data center and the internal square footage
- Google PUE data listing the "3rd facility" from Q3 2025
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.