AI data center · New Carlisle, Indiana
Anthropic-Amazon New Carlisle
Amazon's AI campus in St. Joseph County. It draws about 1.04 GW today and is planned to reach 2.31 GW by March 2028.
Latest look · Oct 19, 2026
What the satellite shows
Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Amazon
- Used by
- Anthropic
- Project
- Project Rainier
- Chips
- Trainium2
- Water use
- 21.00 million gallons a day (Epoch AI estimate)
- Address
- 55001 Larrison Blvd, New Carlisle, IN 46552
- County
- St. Joseph County
Where
On the map of Indiana
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| St Joseph Energy Center | ● Natural gas | 780 MW | 1.1 mi |
| Honeysuckle Solar Farm | ● Solar | 150 MW | 1.8 mi |
| University of Notre Dame | ● Natural gas | 40 MW | 11.6 mi |
| OlivePV | ● Solar | 5 MW | 1.6 mi |
| Southeast Berrien Generating Facility | ● Biomass | 5 MW | 10.6 mi |
| Buchanan (MI) | ● Hydro | 4 MW | 11.5 mi |
| Notre Dame Hydro | ● Hydro | 3 MW | 11.2 mi |
| French Paper Hydro | ● Hydro | 1 MW | 13.6 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Oct 19, 2026 | Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet. | 1.24 GW |
| Jun 3, 2026 | Buildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery. | 1.09 GW |
| Mar 23, 2026 | Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December. | 1.09 GW |
| Feb 9, 2026 | Buildings 12-16 still have a few generators that look incomplete, so they are unlikely to be operational just yet. Buildings 17-18 still have ongoing roof work, no generators. Just south of Buildings 9-16, the outlines of a site for Buildings 19-32 are taking shape. | 751 MW |
| Dec 23, 2025 | Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18. | 751 MW |
| Oct 17, 2025 | Confirmation that nearly 500,000 chips are operational, which fits buildings 1-7. In an interview, AWS CEO says "they're already running...about 500,000 [Trainium2] chips in Indiana today". | 478 MW |
| Sep 26, 2025 | Roof complete on building 16. Generators are being installed for buildings 8-15. In the north, Building 17 and 18 are under construction. To the south of buildings 8-16, a concrete pad is visible, and an expanded car park next to it. | 478 MW |
| Jun 23, 2025 | Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months. | 478 MW |
| May 10, 2025 | Roof complete on building 11 | – |
| Jun 10, 2024 | Land clearing begins in the southern section | – |
| Feb 9, 2024 | Land clearing begins in the northern section | – |
Plus 1 projected step to March 2028, from Epoch AI's reading of the build plans.
How much power does Anthropic-Amazon New Carlisle use?
About 1.04 GW as of Oct 19, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 2.31 GW in its build plans by March 2028. Running all year, 1.04 GW would use about 9.1 TWh.
Who owns Anthropic-Amazon New Carlisle?
Amazon; used by Anthropic. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Anthropic-Amazon New Carlisle?
In St. Joseph County, the average customer is without power about 8.5 hours in a typical year in this site's outage record, with 8 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Anthropic-Amazon New Carlisle?
8 plants within 15 miles total about 988 MW; the largest is St Joseph Energy Center (780 MW, natural gas), 1.1 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Air Construction Permit application for the northern portion
- Backup diesel generator referenced in the permit
- Announcement of Project Rainier coming online
- Air permit for Buildings 19-32, suggesting expansion to 2.3 GW total facility power
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.