AI data center · New Carlisle, Indiana

Anthropic-Amazon New Carlisle

Amazon's AI campus in St. Joseph County. It draws about 1.04 GW today and is planned to reach 2.31 GW by March 2028.

Power now1.04 GWAs of Oct 19, 2026
Planned peak2.31 GWMarch 2028
Compute818kH100-equivalent chips now
Capital cost$39BSo far, 2025 dollars

Latest look · Oct 19, 2026

What the satellite shows

Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.

Build-out

Power, month by month

0 MW500 MW1 GW1.5 GW2 GW2.5 GW2025202620272028Today
Power drawn by Anthropic-Amazon New Carlisle, from Epoch AI's dated observations and (hatched) its projections.
0 MW500 MW1 GW1.5 GW2 GW2.5 GW2025202620272028Today
Power drawn by Anthropic-Amazon New Carlisle, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Amazon
Used by
Anthropic
Project
Project Rainier
Chips
Trainium2
Water use
21.00 million gallons a day (Epoch AI estimate)
Address
55001 Larrison Blvd, New Carlisle, IN 46552
County
St. Joseph County

Where

On the map of Indiana

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
St Joseph Energy Center● Natural gas780 MW1.1 mi
Honeysuckle Solar Farm● Solar150 MW1.8 mi
University of Notre Dame● Natural gas40 MW11.6 mi
OlivePV● Solar5 MW1.6 mi
Southeast Berrien Generating Facility● Biomass5 MW10.6 mi
Buchanan (MI)● Hydro4 MW11.5 mi
Notre Dame Hydro● Hydro3 MW11.2 mi
French Paper Hydro● Hydro1 MW13.6 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Oct 19, 2026Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.1.24 GW
Jun 3, 2026Buildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery.1.09 GW
Mar 23, 2026Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.1.09 GW
Feb 9, 2026Buildings 12-16 still have a few generators that look incomplete, so they are unlikely to be operational just yet. Buildings 17-18 still have ongoing roof work, no generators. Just south of Buildings 9-16, the outlines of a site for Buildings 19-32 are taking shape.751 MW
Dec 23, 2025Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18.751 MW
Oct 17, 2025Confirmation that nearly 500,000 chips are operational, which fits buildings 1-7. In an interview, AWS CEO says "they're already running...about 500,000 [Trainium2] chips in Indiana today".478 MW
Sep 26, 2025Roof complete on building 16. Generators are being installed for buildings 8-15. In the north, Building 17 and 18 are under construction. To the south of buildings 8-16, a concrete pad is visible, and an expanded car park next to it.478 MW
Jun 23, 2025Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.478 MW
May 10, 2025Roof complete on building 11–
Jun 10, 2024Land clearing begins in the southern section–
Feb 9, 2024Land clearing begins in the northern section–

Plus 1 projected step to March 2028, from Epoch AI's reading of the build plans.

How much power does Anthropic-Amazon New Carlisle use?

About 1.04 GW as of Oct 19, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 2.31 GW in its build plans by March 2028. Running all year, 1.04 GW would use about 9.1 TWh.

Who owns Anthropic-Amazon New Carlisle?

Amazon; used by Anthropic. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Anthropic-Amazon New Carlisle?

In St. Joseph County, the average customer is without power about 8.5 hours in a typical year in this site's outage record, with 8 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Anthropic-Amazon New Carlisle?

8 plants within 15 miles total about 988 MW; the largest is St Joseph Energy Center (780 MW, natural gas), 1.1 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.