AI data center · Jeffersonville, Indiana
Meta Jeffersonville
Meta's AI campus in Clark County. It draws about 178 MW today and is planned to reach 241 MW by June 2026.
Latest look · Jun 4, 2026
What the satellite shows
Building 1 and 2 are operational.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Meta
- Used by
- Meta
- Chips
- B300
- Water use
- 0.00 million gallons a day (Epoch AI estimate)
- Address
- 500 8th St, Jeffersonville, IN 47130, USA
- County
- Clark County
Where
On the map of Indiana
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Cane Run | ● Natural gas | 807 MW | 10.5 mi |
| Paddys Run | ● Natural gas | 211 MW | 6.8 mi |
| Ohio Falls | ● Hydro | 110 MW | 2.2 mi |
| Lanesville Solar RES | ● Solar | 1 MW | 13.4 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jun 4, 2026 | Building 1 and 2 are operational. | 241 MW |
| Mar 6, 2026 | Building 1 and 2 shell and cooling look complete, but there's still construction activity. We give it another 3 months to operational. | – |
| Feb 1, 2024 | Land clearing begins. | – |
How much power does Meta Jeffersonville use?
About 178 MW as of Jun 4, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 241 MW in its build plans by June 2026. Running all year, 178 MW would use about 1.6 TWh.
Who owns Meta Jeffersonville?
Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Meta Jeffersonville?
In Clark County, the average customer is without power about 4.3 hours in a typical year in this site's outage record, with 12 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Meta Jeffersonville?
4 plants within 15 miles total about 1.13 GW; the largest is Cane Run (807 MW, natural gas), 10.5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Official Meta Fact Sheet
- Turner Construction contractor presenting their involvement in the project.
- Air Quality Permit for initial buildout
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.