AI data center · Fort Wayne, Indiana

Google Fort Wayne

Google's AI campus in Allen County. It is not drawing power yet and is planned to reach 1.03 GW by June 2028.

Power now–As of Aug 19, 2026
Planned peak1.03 GWJune 2028
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Aug 19, 2026

What the satellite shows

Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. So we give it about 3 more months until it's operational. Building 3 appears to be slightly further than Building 2 was in March, so we estimate a 4-month lag.

Build-out

Power, month by month

0 MW200 MW400 MW600 MW800 MW1 GW1.2 GW2025202620272028Today
Power drawn by Google Fort Wayne, from Epoch AI's dated observations and (hatched) its projections.
0 MW200 MW400 MW600 MW800 MW1 GW1.2 GW2025202620272028Today
Power drawn by Google Fort Wayne, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Google
Used by
Google DeepMind (speculative)
Investors
Google
Address
6015 Adams Center Road, Fort Wayne, IN 46806
County
Allen County

Where

On the map of Indiana

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Paulding Wind Farm II● Wind99 MW14.5 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Aug 19, 2026Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. So we give it about 3 more months until it's operational. Building 3 appears to be slightly further than Building 2 was in March, so we estimate a 4-month lag.–
Mar 1, 2026The cooling towers for Buildings 2 and 3 are both a little less than half done and the buildings still look like active construction sites.–
Oct 1, 2025Building 2 looks externally complete–
Jun 10, 2025After a long quiet period they've laid foundations for Building 2 and the substation.–
Sep 13, 2024Roof complete on Building 1 (the 'H'), although we suspect this building is not for AI compute due to the construction speed, irregular design, and lack of external cooling.–
Apr 1, 2024First signs of development/land clearing–

Plus 5 projected steps to June 2028, from Epoch AI's reading of the build plans.

How much power does Google Fort Wayne use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 1.03 GW by June 2028.

Who owns Google Fort Wayne?

Google; used by Google DeepMind (speculative). Investors: Google. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Fort Wayne?

In Allen County, the average customer is without power about 3.7 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google Fort Wayne?

One plant is within 15 miles: Paulding Wind Farm II (99 MW, wind), 14.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.