Wind power plant · Paulding, OH

Paulding Wind Farm II

Paulding Wind Farm II is a 99 MW wind power plant in Paulding County, Ohio, operated by Paulding Wind Farm II LLC. Its oldest generator still running came online in 2011. In 2025 it generated 318 GWh, about what 30,000 average Ohio homes use in a year.

Capacity99 MWNameplate, September 2026
Generated318 GWhIn 2025
Capacity factor37%Share of the most it could make, 2025
Generators1Oldest from 2011

Paulding Wind Farm II in context

Among the 23 wind plants in Ohio in the EIA's inventory, it is the 7th largest, about 8.0% of the state's 1.2 GW of wind capacity.

Paulding County has 8 power plants of 1 MW or more with 634 MW in all; Paulding Wind Farm II is 16% of that and the 5th largest of 7 wind plants there.

Its capacity factor of 37% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Paulding County goes 5.0 hours a year without power, the 48th most of 88 counties in Ohio. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040020182019202020212022202320242025GWh 318
01002003004002019202120232025318

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Paulding Wind Farm II (outlined) and other plants in Paulding County, shaded. 41.025, -84.779.

Plant facts

Operator
Paulding Wind Farm II LLC
Sector
IPP Non-CHP
Grid operator
PJM
County
Paulding County, OH
EIA plant ID
57620
Where Ohio's power comes from → Ohio power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GEN1 Onshore Wind Turbine 99 MW 2011 –

Nearby

Other plants in Paulding County

Questions

Paulding Wind Farm II, answered

How much power does Paulding Wind Farm II produce?

Paulding Wind Farm II has 99 MW of capacity from one generator. In 2025 it generated 318 GWh, 37% of the most it could have made running flat out all year (its capacity factor).

How many homes does Paulding Wind Farm II power?

Its 2025 output of 318 GWh equals the yearly electricity use of about 30,000 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Paulding Wind Farm II?

Paulding Wind Farm II is in Paulding County, Ohio, at about 41.025°, -84.779°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Paulding County goes 5.0 hours a year without power, the 48th most of 88 counties in Ohio. The county's page has the full outage record.

Who operates Paulding Wind Farm II?

It is operated by Paulding Wind Farm II LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.

When did Paulding Wind Farm II open?

Its oldest generator still running came online in 2011.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.