Data centers · Washington

Data centers in Washington

90 operating data center sites, 10 projects planned or under construction. Washington ranks 10th of 51 by mapped sites.

Operating sites903 whole campuses
AI campuses0None tracked by Epoch AI
In the pipeline105 under construction, 5 planned
Home price13.2¢/kWh+35% since 2018

The map

Every mapped site

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI) Under construction Planned Cancelled

The pipeline

Projects on the way

From Civic Returns, Server Country, AI GridWatch, Megawattlas and the operators' own lists. Size is the developer's announced figure, often a full build-out over years. Projects with no published location are mapped at their city or county.

ProjectDeveloperCountyStatusAnnounced sizeYear
East Wenatchee Campus Microsoft Chelan Under construction 360 MW 2026
Microsoft Malaga Campus Microsoft Chelan Under construction 288 MW 2026
Microsoft East Wenatchee Campus Microsoft Douglas Under construction 180 MW –
Bitdeer Wenatchee (AI cloud conversion) Bitdeer Chelan Under construction – –
Bitfarms (Keel) Moses Lake campus Bitfarms (Keel) Grant Under construction – –
Atlas Agro Richland Data Center Campus Atlas Agro North America Benton Planned 350 MW –
Pacific Northwest National Laboratory On-Premises Next-Gen AI Compute Data Center Pacific Northwest National Laboratory Benton Planned 40 MW 2028
Advance Phase LLC Walla Walla Campus (Project Tree) Amazon Data Services Walla Walla Planned – –
Port of Walla Walla - Project Forest Amazon Data Services, Inc. Walla Walla Planned – 2028
Trammell Crow Lewis & Clark Ranch Data Center Trammell Crow Company Benton Planned – –
Port of Walla Walla - Project Margarita Fortune 100 company Walla Walla Cancelled – –
Port of Walla Walla - Project Network – Walla Walla Cancelled – –

Local pushback

Bans and moratoriums

19 recorded as enacted, 0 proposed or under review, 0 expired, rejected or lifted (AI GridWatch). A time-limited moratorium with no documented end date keeps showing as enacted; check with the town or county.

WhereLevelStatusDateRuns
Lincoln County · Lincoln County Enacted Sep 10, 2026 to Mar 10, 2027
Pierce County · Pierce County Enacted Aug 25, 2026 to Aug 25, 2027
Thurston County · Thurston County Enacted Aug 20, 2026 to Aug 20, 2027
Spokane County · Spokane County Enacted Aug 18, 2026 to Dec 15, 2026
Renton · King Local Enacted Aug 17, 2026 to Aug 17, 2027
Mount Vernon · Skagit Local Enacted Aug 12, 2026 to Feb 12, 2027
Kittitas County · Kittitas Local Enacted Aug 12, 2026 to Feb 12, 2027
Yakima County · Yakima Local Enacted Aug 12, 2026 to Feb 12, 2027
Cle Elum · Kittitas Local Enacted Jul 31, 2026 to Jan 31, 2027
La Conner · Skagit City Enacted Jul 29, 2026 to Jan 29, 2027
Pasco · Franklin Local Enacted Jul 20, 2026 to Jan 20, 2027
Marysville · Snohomish Local Enacted Jul 14, 2026 to Jan 14, 2027
Federal Way · King Local Enacted Jul 7, 2026 to Jul 7, 2027
Burien · King Local Enacted Jun 29, 2026 to Jun 29, 2027
Snohomish County · Snohomish Local Enacted Jun 24, 2026 to Dec 24, 2026

By county

Where the data centers cluster

CountyMapped sitesHours without power a year
Grant County400.3 h
King County257.5 h
Douglas County112.8 h
Snohomish County53.6 h
Spokane County43.6 h
Pierce County23.8 h
Benton County21.3 h
Whatcom County19.7 h

Every named site

The list

65 of 90 operating sites carry a name or operator; the rest are on the map above only. Area is the mapped outline (land for a campus, roof for a building).

SiteOperatorCountySourceAcres
Intergate Columbia Sabey Douglas Campus, 3 buildings 63
Centeris – Pierce Campus, 2 buildings 47
Actapio – Douglas Campus 8.3
Vantage WA13 – Grant Building 5.7
Microsoft EAT02 Microsoft Douglas Building 5.6
Microsoft EAT03 Microsoft Douglas Building 5.4
Microsoft EAT04 Microsoft Douglas Building 5.4
Intergate Seattle East Building 3 Sabey King Building 4.6
Intergate Seattle East Building 5 Sabey King Building 4.6
Microsoft Microsoft Grant Building 3.7
Microsoft Microsoft Grant Building 3.6
Microsoft Microsoft Grant Building 3.4
Microsoft Microsoft Grant Building 3.4
Vantage WA11 – Grant Building 3.4
Microsoft Microsoft Grant Building 3.3
Microsoft Microsoft Grant Building 3.3
Vantage WA12 – Grant Building 2.8
Intergate Seattle East Building 4 Digital Realty King Building 2.7
Microsoft Microsoft Grant Building 2.6
Microsoft Microsoft Grant Building 2.6
Intergate Seattle East Building 2 – King Building 2.4
Centersquare Lynnwood SE1 Centersquare Snohomish Building 2.4
NTT Data Quincy NTT Grant Building 2.3
Intergate Seattle East Building 1 Sabey King Building 2.2
Centersquare SEA2 Centersquare King Civic Returns 1.7

How many data centers are in Washington?

90 operating or permitted sites on this map, from OpenStreetMap, EPA facility records and other open sources: the 10th most of any state. 3 are mapped as whole campuses. The map covers most large sites, not every server room, so the true number is higher.

How many data centers are being built in Washington?

5 under construction and 5 planned or announced in the Civic Returns and Server Country databases; the 5 that publish a size add up to about 1.2 GW. 2 projects have been cancelled.

Which Washington county has the most data centers?

Grant County, with 40 operating sites, then King County (25) and Douglas County (11).

Who operates data centers in Washington?

Among sites that name an operator: Microsoft (11), Sabey (7), Cogent Communications (4), Digital Realty (2), Centersquare (2).

What do Washington households pay for electricity?

13.2¢ per kWh on average in 2025 (US: 17.2¢), up 35% since 2018, from EIA-861. Prices move with fuel, storms and wires spending as well as new demand.

Sources: operating sites from OpenStreetMap © OpenStreetMap contributors (ODbL 1.0), read Nov 17, 2026; operators' own published facility lists; EPA ECHO facility records (public domain); Civic Returns, US Data Centers & Community Benefits Dataset (CC BY 4.0); Overture Maps places (CDLA-Permissive-2.0); Wikidata (CC0); EIA-860. Projects in development from Civic Returns, the Server Country project database, AI GridWatch and Megawattlas (all CC BY 4.0). Moratoriums from AI GridWatch (CC BY 4.0). AI campuses from Epoch AI, "AI data centers", CC BY 4.0. Electricity prices: EIA-861. Outage hours: ORNL EAGLE-I. How this is counted.