AI data center · Muskogee, Oklahoma

CoreWeave Muskogee OK

CoreWeave's AI campus in Muskogee County. It is not drawing power yet and is planned to reach 181 MW by December 2027.

Power now–As of Jun 13, 2026
Planned peak181 MWDecember 2027
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Jun 13, 2026

What the satellite shows

Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operational from all the yard work directly surrounding it, and the lack of a parking lot. Building 2 (The one not leased to CoreWeave) is still in land clearing phase.

Build-out

Power, month by month

0 MW50 MW100 MW150 MW200 MW202520262027Today
Power drawn by CoreWeave Muskogee OK, from Epoch AI's dated observations and (hatched) its projections.
0 MW50 MW100 MW150 MW200 MW202520262027Today
Power drawn by CoreWeave Muskogee OK, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
CoreWeave
Used by
OpenAI (speculative)
Chips
B300
Address
1525 W 43rd St S, Muskogee, OK 74401, USA
County
Muskogee County

Where

On the map of Oklahoma

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Muskogee● Natural gas1.72 GW7 mi
Georgia-Pacific Muskogee● Natural gas114 MW5.6 mi
Fort Gibson● Hydro45 MW14.8 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jun 13, 2026Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operational from all the yard work directly surrounding it, and the lack of a parking lot. Building 2 (The one not leased to CoreWeave) is still in land clearing phase.–
Apr 9, 2026Based on satellite imagery, Building 1 looks mostly complete, but the site still appears to be in construction or commissioning. Not much progress has happened in the past 4 months, and a Q2 2026 finish seems unlikely.–
Nov 18, 2024Core Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center. Core Scientific says the site will provide about 70 MW of critical IT load for CoreWeave's NVIDIA GPUs.–

Plus 2 projected steps to December 2027, from Epoch AI's reading of the build plans.

How much power does CoreWeave Muskogee OK use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 181 MW by December 2027.

Who owns CoreWeave Muskogee OK?

CoreWeave; used by OpenAI (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around CoreWeave Muskogee OK?

In Muskogee County, the average customer is without power about 6.2 hours in a typical year in this site's outage record, with 13 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near CoreWeave Muskogee OK?

3 plants within 15 miles total about 1.88 GW; the largest is Muskogee (1.72 GW, natural gas), 7 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.