AI data center · Los Lunas, New Mexico

Meta Los Lunas

Meta's AI campus in Valencia County. It draws about 118 MW today and is planned to reach 273 MW by January 2028.

Power now118 MWAs of Oct 26, 2026
Planned peak273 MWJanuary 2028
Compute134kH100-equivalent chips now
Capital cost$4.5BSo far, 2025 dollars

Latest look · Oct 26, 2026

What the satellite shows

Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW2025202620272028Today
Power drawn by Meta Los Lunas, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW2025202620272028Today
Power drawn by Meta Los Lunas, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Meta
Used by
Meta
Chips
B300
Water use
0.00 million gallons a day (Epoch AI estimate)
Address
4250 Messenger Lp, Los Lunas, NM 87031
County
Valencia County

Where

On the map of New Mexico

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Sky Ranch Solar● Solar240 MW3.4 mi
Sky Ranch BESS II● Storage100 MW3.4 mi
La Luz Energy Center● Natural gas42 MW14.9 mi
Santolina Solar Energy Center● Solar11 MW14.4 mi
South Valley Solar Energy Center● Solar10 MW11.1 mi
Facebook 1 Solar Energy Center● Solar10 MW1.2 mi
Vista Solar Energy Center● Solar10 MW9.6 mi
Rio De Oro Solar Energy Center● Solar10 MW11 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Oct 26, 2026Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.147 MW
Jul 28, 2026Building 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months (it's been 10 months for this building). North-west of Building 1, the outline of a building of similar dimensions and style to Meta Jeffersonville's Building 1 is visible, this is labeled as Building 3. West of Building 1 we see more land clearing for what could be a building similar to Meta Jeffersonville's Building 2.114 MW
Mar 1, 2026Building 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion.114 MW
Jul 24, 2024Land clearing starts for new building.–

Plus 1 projected step to January 2028, from Epoch AI's reading of the build plans.

How much power does Meta Los Lunas use?

About 118 MW as of Oct 26, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 273 MW in its build plans by January 2028. Running all year, 118 MW would use about 1.0 TWh.

Who owns Meta Los Lunas?

Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Meta Los Lunas?

In Valencia County, the average customer is without power about 3.8 hours in a typical year in this site's outage record, with 14 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Meta Los Lunas?

8 plants within 15 miles total about 466 MW; the largest is Sky Ranch Solar (240 MW, solar), 3.4 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.