AI data center · Los Lunas, New Mexico
Meta Los Lunas
Meta's AI campus in Valencia County. It draws about 118 MW today and is planned to reach 273 MW by January 2028.
Latest look · Oct 26, 2026
What the satellite shows
Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Meta
- Used by
- Meta
- Chips
- B300
- Water use
- 0.00 million gallons a day (Epoch AI estimate)
- Address
- 4250 Messenger Lp, Los Lunas, NM 87031
- County
- Valencia County
Where
On the map of New Mexico
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Sky Ranch Solar | ● Solar | 240 MW | 3.4 mi |
| Sky Ranch BESS II | ● Storage | 100 MW | 3.4 mi |
| La Luz Energy Center | ● Natural gas | 42 MW | 14.9 mi |
| Santolina Solar Energy Center | ● Solar | 11 MW | 14.4 mi |
| South Valley Solar Energy Center | ● Solar | 10 MW | 11.1 mi |
| Facebook 1 Solar Energy Center | ● Solar | 10 MW | 1.2 mi |
| Vista Solar Energy Center | ● Solar | 10 MW | 9.6 mi |
| Rio De Oro Solar Energy Center | ● Solar | 10 MW | 11 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Oct 26, 2026 | Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July. | 147 MW |
| Jul 28, 2026 | Building 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months (it's been 10 months for this building). North-west of Building 1, the outline of a building of similar dimensions and style to Meta Jeffersonville's Building 1 is visible, this is labeled as Building 3. West of Building 1 we see more land clearing for what could be a building similar to Meta Jeffersonville's Building 2. | 114 MW |
| Mar 1, 2026 | Building 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion. | 114 MW |
| Jul 24, 2024 | Land clearing starts for new building. | – |
Plus 1 projected step to January 2028, from Epoch AI's reading of the build plans.
How much power does Meta Los Lunas use?
About 118 MW as of Oct 26, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 273 MW in its build plans by January 2028. Running all year, 118 MW would use about 1.0 TWh.
Who owns Meta Los Lunas?
Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Meta Los Lunas?
In Valencia County, the average customer is without power about 3.8 hours in a typical year in this site's outage record, with 14 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Meta Los Lunas?
8 plants within 15 miles total about 466 MW; the largest is Sky Ranch Solar (240 MW, solar), 3.4 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.