AI data center · Santa Teresa, New Mexico

OpenAI Stargate New Mexico

Oracle's AI campus in Doña Ana County. It is not drawing power yet and is planned to reach 2.45 GW by December 2028.

Power now–As of Jun 22, 2026
Planned peak2.45 GWDecember 2028
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Jun 22, 2026

What the satellite shows

Construction has advanced significantly since February 2026. We observe extensive earthworks and multiple graded building pads across the campus, with structural work underway on the main data center buildings. A large solar array and water storage basins are visible on site, and two cleared areas on the western side of the campus, likely for on-site power generation. No buildings appear operational yet (no completed roofs or signs of active cooling), consistent with the projected 2028 completion.

Build-out

Power, month by month

0 MW1 GW2 GW3 GW202620272028Today
Power drawn by OpenAI Stargate New Mexico, from Epoch AI's dated observations and (hatched) its projections.
0 MW1 GW2 GW3 GW202620272028Today
Power drawn by OpenAI Stargate New Mexico, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Oracle
Used by
OpenAI
Project
Stargate
Energy companies
Bloom Energy
Water use
0.00 million gallons a day (Epoch AI estimate)
County
Doña Ana County (approximate)

Where

On the map of New Mexico

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Santa Teresa, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Rio Grande● Natural gas348 MW8.7 mi
Milagro Solar I● Solar225 MW5.5 mi
Santa Teresa Solar● Solar150 MW4.8 mi
Roadrunner Solar● Solar20 MW5.4 mi
Tenet Hospital● Natural gas4 MW12.3 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jun 22, 2026Construction has advanced significantly since February 2026. We observe extensive earthworks and multiple graded building pads across the campus, with structural work underway on the main data center buildings. A large solar array and water storage basins are visible on site, and two cleared areas on the western side of the campus, likely for on-site power generation. No buildings appear operational yet (no completed roofs or signs of active cooling), consistent with the projected 2028 completion.–
Feb 6, 2026Land clearing continues, foundation construction begins 2 of the main buildings (Building B & D). Construction also beginning on modular chiller plants.–
Oct 1, 2025Construction and land clearing begins–

Plus 1 projected step to December 2028, from Epoch AI's reading of the build plans.

How much power does OpenAI Stargate New Mexico use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 2.45 GW by December 2028.

Who owns OpenAI Stargate New Mexico?

Oracle; used by OpenAI. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around OpenAI Stargate New Mexico?

In Doña Ana County, the average customer is without power about 2.4 hours in a typical year in this site's outage record, with 5 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near OpenAI Stargate New Mexico?

5 plants within 15 miles total about 748 MW; the largest is Rio Grande (348 MW, natural gas), 8.7 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.