AI data center · Santa Teresa, New Mexico
OpenAI Stargate New Mexico
Oracle's AI campus in Doña Ana County. It is not drawing power yet and is planned to reach 2.45 GW by December 2028.
Latest look · Jun 22, 2026
What the satellite shows
Construction has advanced significantly since February 2026. We observe extensive earthworks and multiple graded building pads across the campus, with structural work underway on the main data center buildings. A large solar array and water storage basins are visible on site, and two cleared areas on the western side of the campus, likely for on-site power generation. No buildings appear operational yet (no completed roofs or signs of active cooling), consistent with the projected 2028 completion.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Oracle
- Used by
- OpenAI
- Project
- Stargate
- Energy companies
- Bloom Energy
- Water use
- 0.00 million gallons a day (Epoch AI estimate)
- County
- Doña Ana County (approximate)
Where
On the map of New Mexico
Placed at the centre of Santa Teresa, as no address could be matched, so the dot and the county are approximate.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Rio Grande | ● Natural gas | 348 MW | 8.7 mi |
| Milagro Solar I | ● Solar | 225 MW | 5.5 mi |
| Santa Teresa Solar | ● Solar | 150 MW | 4.8 mi |
| Roadrunner Solar | ● Solar | 20 MW | 5.4 mi |
| Tenet Hospital | ● Natural gas | 4 MW | 12.3 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jun 22, 2026 | Construction has advanced significantly since February 2026. We observe extensive earthworks and multiple graded building pads across the campus, with structural work underway on the main data center buildings. A large solar array and water storage basins are visible on site, and two cleared areas on the western side of the campus, likely for on-site power generation. No buildings appear operational yet (no completed roofs or signs of active cooling), consistent with the projected 2028 completion. | – |
| Feb 6, 2026 | Land clearing continues, foundation construction begins 2 of the main buildings (Building B & D). Construction also beginning on modular chiller plants. | – |
| Oct 1, 2025 | Construction and land clearing begins | – |
Plus 1 projected step to December 2028, from Epoch AI's reading of the build plans.
How much power does OpenAI Stargate New Mexico use?
It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 2.45 GW by December 2028.
Who owns OpenAI Stargate New Mexico?
Oracle; used by OpenAI. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around OpenAI Stargate New Mexico?
In Doña Ana County, the average customer is without power about 2.4 hours in a typical year in this site's outage record, with 5 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near OpenAI Stargate New Mexico?
5 plants within 15 miles total about 748 MW; the largest is Rio Grande (348 MW, natural gas), 8.7 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Project Jupiter Website
- Stormwater Permitting
- Oracle, BorderPlex and Bloom Energy to power Project Jupiter with fuel cell technology (Apr 27, 2026)
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.