AI data center · Cedar Rapids, Iowa
Google Cedar Rapids
Google's AI campus in Linn County. It is not drawing power yet and is planned to reach 314 MW by May 2027.
Latest look · Apr 16, 2026
What the satellite shows
Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers and generators.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Used by
- Google DeepMind (speculative)
- Address
- 5800 EDGEWOOD RD SW CEDAR RAPIDS, IA 52404
- County
- Linn County
Where
On the map of Iowa
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Archer Daniels Midland Cedar Rapids | ● Coal | 295 MW | 1.4 mi |
| Prairie Creek | ● Natural gas | 199 MW | 4.2 mi |
| Pleasant Creek Unit 2 | ● Solar | 150 MW | 13.1 mi |
| Pleasant Creek Unit 1 | ● Solar | 50 MW | 13.1 mi |
| Amana Society Service Company | ● Oil | 22 MW | 12.7 mi |
| Alliant SBD 9106 Rockwell CR | ● Oil | 16 MW | 8.6 mi |
| Alliant SBD0201 Ingredion | ● Oil | 6 MW | 4.2 mi |
| Alliant SBD 8602 Marion Sub | ● Oil | 6 MW | 9.6 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Apr 16, 2026 | Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers and generators. | – |
| Dec 29, 2025 | About half of Building 1 generators are in place. Building 2 roofing has started - about where Google Omaha Building 3 was on 2025-03-16. | – |
| Oct 27, 2025 | Building 1 cooling towers and generators starting to be put in place. There's a foundation for Building 2 and 3. | – |
| Jun 14, 2024 | Land clearing begins. | – |
Plus 3 projected steps to May 2027, from Epoch AI's reading of the build plans.
How much power does Google Cedar Rapids use?
It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 314 MW by May 2027.
Who owns Google Cedar Rapids?
Google; used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google Cedar Rapids?
In Linn County, the average customer is without power about 18 hours in a typical year in this site's outage record, with 3 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google Cedar Rapids?
8 plants within 15 miles total about 762 MW; the largest is Archer Daniels Midland Cedar Rapids (295 MW, coal), 1.4 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.