AI data center · Cedar Rapids, Iowa

Google Cedar Rapids

Google's AI campus in Linn County. It is not drawing power yet and is planned to reach 314 MW by May 2027.

Power now–As of Apr 16, 2026
Planned peak314 MWMay 2027
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Apr 16, 2026

What the satellite shows

Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers and generators.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW202520262027Today
Power drawn by Google Cedar Rapids, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW400 MW202520262027Today
Power drawn by Google Cedar Rapids, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Google
Used by
Google DeepMind (speculative)
Address
5800 EDGEWOOD RD SW CEDAR RAPIDS, IA 52404
County
Linn County

Where

On the map of Iowa

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Archer Daniels Midland Cedar Rapids● Coal295 MW1.4 mi
Prairie Creek● Natural gas199 MW4.2 mi
Pleasant Creek Unit 2● Solar150 MW13.1 mi
Pleasant Creek Unit 1● Solar50 MW13.1 mi
Amana Society Service Company● Oil22 MW12.7 mi
Alliant SBD 9106 Rockwell CR● Oil16 MW8.6 mi
Alliant SBD0201 Ingredion● Oil6 MW4.2 mi
Alliant SBD 8602 Marion Sub● Oil6 MW9.6 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Apr 16, 2026Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers and generators.–
Dec 29, 2025About half of Building 1 generators are in place. Building 2 roofing has started - about where Google Omaha Building 3 was on 2025-03-16.–
Oct 27, 2025Building 1 cooling towers and generators starting to be put in place. There's a foundation for Building 2 and 3.–
Jun 14, 2024Land clearing begins.–

Plus 3 projected steps to May 2027, from Epoch AI's reading of the build plans.

How much power does Google Cedar Rapids use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 314 MW by May 2027.

Who owns Google Cedar Rapids?

Google; used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Cedar Rapids?

In Linn County, the average customer is without power about 18 hours in a typical year in this site's outage record, with 3 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google Cedar Rapids?

8 plants within 15 miles total about 762 MW; the largest is Archer Daniels Midland Cedar Rapids (295 MW, coal), 1.4 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.