AI data center · Cumming, Iowa

Microsoft Project Osmium

Microsoft's AI campus in Warren County. It draws about 190 MW today and is planned to reach 228 MW by March 2025.

Power now190 MWAs of Jun 16, 2026
Planned peak228 MWMarch 2025
Compute156kH100-equivalent chips now
Capital cost$7.2BSo far, 2025 dollars

Latest look · Jun 16, 2026

What the satellite shows

No notable changes since October.

Build-out

Power, month by month

0 MW50 MW100 MW150 MW200 MW250 MW20192020202120222023202420252026
Power drawn by Microsoft Project Osmium, from Epoch AI's dated observations.
0 MW50 MW100 MW150 MW200 MW250 MW2020202220242026
Power drawn by Microsoft Project Osmium, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Microsoft
Used by
OpenAI (speculative)
Chips
A100, H100, B200
Address
5855 SW Kerry St, Cumming, IA 50061
County
Warren County (approximate)

Where

On the map of Iowa

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Cumming, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Greater Des Moines● Natural gas576 MW13.1 mi
Pleasant Hill● Natural gas180 MW13.3 mi
Sycamore (IA)● Natural gas158 MW13.7 mi
River Hills● Natural gas128 MW10.4 mi
Indianola● Oil41 MW13.4 mi
Archer Daniels Midland Des Moines● Natural gas8 MW13.3 mi
Indianola Solar● Solar3 MW13.8 mi
Des Moines Wastewater Reclamation Fac● Biomass3 MW12.2 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jun 16, 2026No notable changes since October.228 MW
Oct 8, 2025Site already complete.228 MW
Mar 1, 2025Building 3-4 operational, no visible construction.228 MW
Jun 30, 2023Building 2 is operational. Estimated based on Microsoft H100 count 2023114 MW
Jan 1, 2021Building 1 and 1st building on the site are operational. Foundation work begins on Building 257 MW
Dec 18, 2018Land clearing begins on the north part of the site–

How much power does Microsoft Project Osmium use?

About 190 MW as of Jun 16, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 228 MW in its build plans by March 2025. Running all year, 190 MW would use about 1.7 TWh.

Who owns Microsoft Project Osmium?

Microsoft; used by OpenAI (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Microsoft Project Osmium?

In Warren County, the average customer is without power about 2.5 hours in a typical year in this site's outage record, with 9 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Microsoft Project Osmium?

8 plants within 15 miles total about 1.10 GW; the largest is Greater Des Moines (576 MW, natural gas), 13.1 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.