AI data center · Cedar Rapids, Iowa

QTS Cedar Rapids

Meta's AI campus in Linn County. It is not drawing power yet and is planned to reach 1.59 GW by November 2027.

Power now–As of Oct 23, 2026
Planned peak1.59 GWNovember 2027
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Oct 23, 2026

What the satellite shows

Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared. The many cars and trucks parked beside the buildings suggest commissioning is still underway, so we’re not counting any buildings operational yet. Buildings 4-6 shells appear complete, and Building 7 is nearly 90% roofed. This is based on high-resolution satellite imagery from this date.

Build-out

Power, month by month

0 MW500 MW1 GW1.5 GW2 GW202520262027Today
Power drawn by QTS Cedar Rapids, from Epoch AI's dated observations and (hatched) its projections.
0 MW500 MW1 GW1.5 GW2 GW202520262027Today
Power drawn by QTS Cedar Rapids, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Meta (speculative)
Used by
Meta (speculative)
Energy companies
Alliant Energy
Chips
B300, Rubin
Address
6200 76th Ave SW, Fairfax, IA 52228
County
Linn County

Where

On the map of Iowa

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Archer Daniels Midland Cedar Rapids● Coal295 MW3.5 mi
Prairie Creek● Natural gas199 MW6.3 mi
Pleasant Creek Unit 2● Solar150 MW13.8 mi
Pleasant Creek Unit 1● Solar50 MW13.8 mi
Amana Society Service Company● Oil22 MW10.6 mi
Alliant SBD 9106 Rockwell CR● Oil16 MW10.5 mi
Alliant SBD0201 Ingredion● Oil6 MW6.2 mi
Alliant SBD 8602 Marion Sub● Oil6 MW11.6 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Oct 23, 2026Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared. The many cars and trucks parked beside the buildings suggest commissioning is still underway, so we’re not counting any buildings operational yet. Buildings 4-6 shells appear complete, and Building 7 is nearly 90% roofed. This is based on high-resolution satellite imagery from this date.–
May 7, 2026Similar to April, Buildings 1-3 shells look complete. Buildings 4-6 are still far along, and the eastern Building 7 foundation is still underway.–
Apr 16, 2026Based on satellite imagery, the Buildings 1-3 shells look complete. Buildings 4-6 are far along, with roofs largely in place, while the eastern Building 7 foundation is well underway. No buildings operational yet.–
Oct 27, 2025Building 1 roof complete, with air-cooled chillers in place. Building 2 and 3 roofs are partly completed. Building 4 and 5 have a foundation.–
Jan 17, 2025Land clearing begins for Building 1-3.–

Plus 2 projected steps to November 2027, from Epoch AI's reading of the build plans.

How much power does QTS Cedar Rapids use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 1.59 GW by November 2027.

Who owns QTS Cedar Rapids?

Meta (speculative); used by Meta (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around QTS Cedar Rapids?

In Linn County, the average customer is without power about 18 hours in a typical year in this site's outage record, with 3 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near QTS Cedar Rapids?

8 plants within 15 miles total about 765 MW; the largest is Archer Daniels Midland Cedar Rapids (295 MW, coal), 3.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus