AI data center · Cedar Rapids, Iowa
QTS Cedar Rapids
Meta's AI campus in Linn County. It is not drawing power yet and is planned to reach 1.59 GW by November 2027.
Latest look · Oct 23, 2026
What the satellite shows
Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared. The many cars and trucks parked beside the buildings suggest commissioning is still underway, so we’re not counting any buildings operational yet. Buildings 4-6 shells appear complete, and Building 7 is nearly 90% roofed. This is based on high-resolution satellite imagery from this date.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Meta (speculative)
- Used by
- Meta (speculative)
- Energy companies
- Alliant Energy
- Chips
- B300, Rubin
- Address
- 6200 76th Ave SW, Fairfax, IA 52228
- County
- Linn County
Where
On the map of Iowa
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Archer Daniels Midland Cedar Rapids | ● Coal | 295 MW | 3.5 mi |
| Prairie Creek | ● Natural gas | 199 MW | 6.3 mi |
| Pleasant Creek Unit 2 | ● Solar | 150 MW | 13.8 mi |
| Pleasant Creek Unit 1 | ● Solar | 50 MW | 13.8 mi |
| Amana Society Service Company | ● Oil | 22 MW | 10.6 mi |
| Alliant SBD 9106 Rockwell CR | ● Oil | 16 MW | 10.5 mi |
| Alliant SBD0201 Ingredion | ● Oil | 6 MW | 6.2 mi |
| Alliant SBD 8602 Marion Sub | ● Oil | 6 MW | 11.6 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Oct 23, 2026 | Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared. The many cars and trucks parked beside the buildings suggest commissioning is still underway, so we’re not counting any buildings operational yet. Buildings 4-6 shells appear complete, and Building 7 is nearly 90% roofed. This is based on high-resolution satellite imagery from this date. | – |
| May 7, 2026 | Similar to April, Buildings 1-3 shells look complete. Buildings 4-6 are still far along, and the eastern Building 7 foundation is still underway. | – |
| Apr 16, 2026 | Based on satellite imagery, the Buildings 1-3 shells look complete. Buildings 4-6 are far along, with roofs largely in place, while the eastern Building 7 foundation is well underway. No buildings operational yet. | – |
| Oct 27, 2025 | Building 1 roof complete, with air-cooled chillers in place. Building 2 and 3 roofs are partly completed. Building 4 and 5 have a foundation. | – |
| Jan 17, 2025 | Land clearing begins for Building 1-3. | – |
Plus 2 projected steps to November 2027, from Epoch AI's reading of the build plans.
How much power does QTS Cedar Rapids use?
It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 1.59 GW by November 2027.
Who owns QTS Cedar Rapids?
Meta (speculative); used by Meta (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around QTS Cedar Rapids?
In Linn County, the average customer is without power about 18 hours in a typical year in this site's outage record, with 3 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near QTS Cedar Rapids?
8 plants within 15 miles total about 765 MW; the largest is Archer Daniels Midland Cedar Rapids (295 MW, coal), 3.5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- MISO new load announcements
- Article by The Gazette
- Article by Corridor Business Journal
- Post by GLD Commercial
- Post by SemiAnalysis
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.